Q. Explain about water De-Oiling process?
The De-Oiling process consists of three major components:
The inlet stream to the Surge Tank can be dosed with de-oiling polymer to assist with emulsion breaking. PW flows from the Surge Tank by gravity. Entrained oil accumulates and floats as a top liquid layer in the Surge Tank. The Surge Tank is connected to the VRU gathering system to collect the vapours that will normally evolve from the water as the pressure is reduced on the inlet to the tank.
The Skim Tank accepts PW from Surge Tank. The function of this tank is to reduce oil content from 1000 ppm to 100 ppm. Oil skimming is carried out intermittently from the compartment. Skim Tank is also connected to the VRU gathering system.
The function of IGF package is to reduce oil content from 100 to 10 ppm. The IGF technology uses a combination of chemical and gas bubbles to accelerate oil-water separation. De-oiling polymer can be injected into the stream of the package to facilitate the agglomeration of the froth. Gas is induced hydraulically, driven by Eductor Pumps.
Water from the IGF De-Oiled water compartment is pumped to the ORF Package for the final De-Oiling Stage. The ORF package reduces the oil content further to less than 2ppm. The De-oiled PW is collected in the De-Oiled Water Tank for storage before further processing in the Water Treatment Plant.
Grinding & Brushing: Grinding is process there has an abrasive wheel that rotating at certain speed to smooth a surface or to give an even finish on material. In this Blade pr
velocity ratio is 3 .pinion has 40 teeth. what would be the gear no of teeth?
Shear and Moment Diagrams Determine the analytical solution for the maximum stress of the beam shown; compare with stress results from Solid Works. Draw shear and moment diagra
general characteristic of bulk deformation and different process and corresponding product properties
Wall-type bunds / dikes for storage compounds should be from 0.5 m to 1.5 m high (1.5 ft. - 5 ft. - check local codes and regulations), depending on the required containment capaci
Q. Design Loads and Load Combinations? The Designer shall determine the following loads and specify them on the Data Sheet. Design loads are defined and classified as follows:
what do you mean by law of belting and also explain the crowning of pulleys ?
which book is prefferable for plant maintenance?
what are the essentials of a good steam generator?
Can you prove an equation from Plane Stress and Plane strain?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd