Roads in hilly areas, Civil Engineering

Assignment Help:

Roads in Hilly Areas:

(a)        The alignment selected should attain the changes in elevation by adopting the ruling gradient to the maximum length. Limiting and exceptional gradients should be avoided as far as possible.

(b)       Avoid deep cuttings, high embankments and costly tunnels.

(c)        Areas prone to landslides and subsidences should be avoided.

(d)       Areas liable to snow drift and avalanches should be avoided.

(e)        Obligatory points such as bridges, passes and tunnels should be identified first and the alignment shall be selected to match with them.

(f)        Sunny side of exposed hill is preferred.

(g)       Hairpin bends should be avoided as far as possible. If unavoidable, they should be located on gentle hill slopes.

(h)       The main object of a hill road is to gain elevation. Thus, alternate rise and fall should be avoided.


Related Discussions:- Roads in hilly areas

What do you mean by base fixity, Q. What do you mean by Base fixity? B...

Q. What do you mean by Base fixity? Base fixity When structures such as portal frames are associated to the base foundation, engineers have to determine the degree of fix

Bituminous macadam, What is the working capacity of a road paver per hour f...

What is the working capacity of a road paver per hour for bituminous macadam

Mechanics of solids assignment, What will be the cost of Mechanics of solid...

What will be the cost of Mechanics of solids assignment consisting of 150 questions of 6 marks

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Test on complete bearings, Q. Test on complete bearings? Two bearings s...

Q. Test on complete bearings? Two bearings should be selected at random from the 'lot'. Various tests should be conducted on these 'test bearings'. These bearings should be exc

Calculate the total cost for the project, The total equipment cost for an a...

The total equipment cost for an addition to a pharmaceutical plant is estimated to be $5,000,000. The percentages provided in the Table represent the average expenditures in other

Deflections of bars, how do one uses the Macauleys model to find deflection...

how do one uses the Macauleys model to find deflections of bars

What is bonded post-tensioning, What is Bonded Post-tensioning In post...

What is Bonded Post-tensioning In post-tensioned construction, ducts, in which tendons are provided, are sometimes grouted after the stressing operation. Though the mechanism

What is the force exerted by the tacoma narrows bridge, The force exerted t...

The force exerted to the Tacoma narrows bridge was initially the wind resistance. The wind resistance cause the entire bridge to act as a system with forced vibration with damping.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd