Road location in dune areas, Civil Engineering

Assignment Help:

Road Location in Dune Areas:

The following principle should be observed in locating a road in dune areas :

(a) Align a road where sand is covered by vegetation.

(b) Select a location where the sand is coarse and cannot be blown by wind.

(c) If a road has to be aligned parallel to a sand ridge, avoid locating the road on the slopes. Locate the road either at the top of the ridge or in the inter-dunal space.

(d) If possible locate the road away from the dune at a minimum distance of twice the dune height.

The details of the location of roads placed in dune areas are given in Figure.

2357_Road Location in Dune Areas.png

Figure : Possible Locations of Road in Sand Ridge

The following guidelines may be observed in design :

(a) Avoid sections with partial cut and partial fill.

(b) Avoid cut sections as far as possible.

(c) Avoid high road embankments.

(d) When cutting is done in dunes, provide benchings 5-8 m wide.

(e) It is preferable to black-top the road, since unsurfaced pavements can get dislodged when the sand deposit is cleared by a grader.

(f) Precast concrete blocks are also be good surfacing specification since the cost of maintenance is minimised.


Related Discussions:- Road location in dune areas

Compute the maximum allowable concentrated live load, Given for the section...

Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac

Compaction to freshly placed concrete piles, Compaction to freshly placed c...

Compaction to freshly placed concrete piles  In general practice, reliance is placed on the self-compaction of particularly designed concrete mixes to achieve adequate compact

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Hydraulics, A rectangular channel, 20ft wide is shown. The channel consists...

A rectangular channel, 20ft wide is shown. The channel consists of three reaches of different slopes. The channel has a roughness coefficient of n=0.015 and carries a discharge of

Insulating washer between steel bolts and aluminium plates, Q. Insulating w...

Q. Insulating washer between steel bolts and aluminium plates? Corrosion of aluminium can be activated by putting it in contact with another metal in the presence of water. Thi

What is meaning of washers while using bolts, Question What is meaning ...

Question What is meaning of washers while using bolts? Answer Purpose of installing washers in a classic bolting system is to distribute loads under bolt heads and nu

Levelling, Permanent adjustment and temporary adjustment

Permanent adjustment and temporary adjustment

Building Drawing, Illustrate by mean of single line drawing the difference ...

Illustrate by mean of single line drawing the difference between couple truss and couple close truss

Sieve analysis, size of sieve to analysis the grading of 10 mm size stone g...

size of sieve to analysis the grading of 10 mm size stone grit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd