Road base and base course in flexible carriageway, Civil Engineering

Assignment Help:

Road base vs. base course in flexible carriageway

Roadbase is the most significant structural layer in bituminous pavement. It's designed to take up the function of distributing the traffic loads so as not to exceed the bearing capacity of subgrade. Additionally it helps to provide sufficient resistance to fatigue under cyclic loads and to provide a higher stiffness for the pavement structure. 

Though the basecourse is generally provided to give a well-prepared and even surface for the laying on wearing course. Regarding the load distribution function, it also assists to spread traffic loads to roadbase however this isn't the primary function of basecourse.


Related Discussions:- Road base and base course in flexible carriageway

State the increase in earth pressure at rest, A wall with a smooth vertical...

A wall with a smooth vertical back and 9 metres high retains a moist cohesionless soil with a horizontal surface. The soil weighs 15 kN/m3 and has an angle of internal friction of

Determine the in-situ dry unit weight, Q. The following observations were r...

Q. The following observations were recorded in a Field density determination by sand-replacement method: Volume of Calibrating can = 1000 cm3 Weight of empty can = 10 N We

Whole barings, Ask question #Minexaple of wholeiwhole baring 100 words acce...

Ask question #Minexaple of wholeiwhole baring 100 words accepted#

Define recommendations for design of ptfe sliding bearing, Define Recommend...

Define Recommendations for Design of PTFE Sliding Bearing? Other Recommendations for Design of PTFE Sliding Bearing 1. Expansion bearings having sliding surfaces of PTFE sha

Drainage of embankment slopes, Drainage of Embankment Slopes: Slopes ...

Drainage of Embankment Slopes: Slopes of high embankments get eroded by rain water. Deep rain cuts are formed, which endanger the pavement. In such cases, it is customary to

Construction Planning, A contractor has both a 3-cy and a 5-cy shovel in th...

A contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working day

Basic, what you mean by civil engineering

what you mean by civil engineering

Major compensation of using hdpe as compared with cast iron, Question N...

Question Now, mainly flap valves are ended of HDPE. What is the major compensation of using HDPE as compared with cast iron? Answer (i) It has no response with sewage

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd