Q. Resource usage with reference to software reliability models?

Resource usage: It is linearly proportional to implementation time t and mean failures experienced μ. Let Xr be the usage of resource r.

Then

Xr = qrt+μrμ

Where qr is the resource usage per CPU hr. It is nonzero for failure identification personnel (qi) as well as computer time (qc). The quantity μr is the resource usage per failure. It is nonzero for failure identification personnel (μi), failure correction personnel (μf) and computer time (μc).


Related Discussions:- Resource usage with reference to software reliability models

Script file, how to make script file volume of pyramid

how to make script file volume of pyramid

What is the difference between testing and quality assurance, Differentiate...

Differentiate between testing and QA. - Quality Assurance is more a preventive thing, which ensures quality in company and hence the product instead of just testing the product

Describe design walk throughs and critical design review, Q. Describe desig...

Q. Describe design walk throughs and critical design review. Ans. A design walkthrough is a excellence practice that allows designers to acquire an early validation of desi

What do you mean by reverse engineering, Q. What do you mean by REVERSE ENG...

Q. What do you mean by REVERSE ENGINEERING? REVERSE ENGINEERING:-It is a process of analyzing software with a outlook to understanding its design and specification. In t

What is incremental testing, Incremental testing is fractional testing of a...

Incremental testing is fractional testing of an incomplete product. The aim of incremental testing is to give an early feedback to software developers.

Determine the working of developer of software, Determine the working of de...

Determine the working of developer of Software As developer of Software and user of Software became separate organisation, business concepts such as software costing, Software

Configuration management, Configuration Management: Because of several ...

Configuration Management: Because of several reasons, software changes during its life cycle. As a result of the changes made, many versions of the software exist at one time.

Event procedure and a general procedure, (a) Visual Basic is governed by an...

(a) Visual Basic is governed by an event processor. Explain the meaning of this phrase. (b) Differentiate between an event procedure and a general procedure. (c) "For datab

Project or process, Mentoring a class at a university. is project or proce...

Mentoring a class at a university. is project or process??

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd