Remedial proposal to rectify situation, Civil Engineering

Assignment Help:

Question

During deep excavation, neighbouring ground water table is drawn down that might affect settlement of nearby buildings. What is remedial proposal to rectify situation?


Answer

One of methods to manage settlement of nearby buildings Because of excavation work is by recharging. Water composed in wells in deep excavation is place back to top of excavation in order to raise drawn-down water table. Location of recharge has to be properly selected to ensure soil is adequately permeable to transfer pumped water back near pretentious building.

 

 


Related Discussions:- Remedial proposal to rectify situation

Explain pressure balance method and compressed air method, Pressure balance...

Pressure balance method vs. compressed air method in pipe jacking Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutti

What is thermo-electric prestressing, What is Thermo-electric prestressing ...

What is Thermo-electric prestressing We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other mea

Reinforced Concrete Design, design a 3-meter cantilever slab to carry a uni...

design a 3-meter cantilever slab to carry a uniform total dead load of 8.2KN/m^2 and a concentrated live load at the free end of 30 KN/m. f''c=28Mpa fy=420Mpa.

Case of multi speed restrictions, Q. Case of Multi speed restrictions? ...

Q. Case of Multi speed restrictions? Position of Engineering indicators in case of Multi speed restrictions on one of the line in a Double line section where the first speed re

Design the transverse shear reinforcement, Details of a simply-supported be...

Details of a simply-supported beam are given in Figures (a) and (b). Note that the dead load, g includes the self weight. Design the transverse shear reinforcement in ter

Mechanics of solids, Ask question #MinThe maximum instantaneous extension, ...

Ask question #MinThe maximum instantaneous extension, produced by an unknown falling weight through a height of 4 cm in a vertical bar of length 3 m and of cross sectional area 5 c

Explain coagulation - Surface Water, Explain Coagulation Surface wa...

Explain Coagulation Surface waters must be treated to remove turbidity, color and bacteria The traditional sand filtration is not sufficient in removing bacteria, viru

Define vertical curves - transportation, Define Vertical Curves  - Transpor...

Define Vertical Curves  - Transportation 1) Vertical curves are used to change the grade of a highway. 2) Most vertical curves take the shape of an equal-tangent parabola.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd