Remedial proposal to rectify situation, Civil Engineering

Assignment Help:

Question

During deep excavation, neighbouring ground water table is drawn down that might affect settlement of nearby buildings. What is remedial proposal to rectify situation?


Answer

One of methods to manage settlement of nearby buildings Because of excavation work is by recharging. Water composed in wells in deep excavation is place back to top of excavation in order to raise drawn-down water table. Location of recharge has to be properly selected to ensure soil is adequately permeable to transfer pumped water back near pretentious building.

 

 


Related Discussions:- Remedial proposal to rectify situation

Determine the expected extension at the jack, A cylindrical concrete tank,...

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  10 5   N/mm 2 )  jacked  at 4 points, 9

Compass survey, define compass survey and mention its objectives

define compass survey and mention its objectives

Concrete compaction in piling works, Question What is the reason that v...

Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i

Priciples of working from whole to part in surveying, What are the principl...

What are the principles of working from whole to part in surveying?

Stabilization of Black Cotton soil, How the stabilization of black cotton ...

How the stabilization of black cotton soil was done in field? what are the methods to do that?

Calculate the flood discharg, Q. A bridge is to be constructed over a strea...

Q. A bridge is to be constructed over a stream having a catchment area = 20 miles 2 partly in plains and partly in hills. Portion in hills has a length of 1.7 miles and fall of 88

Surveying, What is the least count of prismatic and surveyor compass

What is the least count of prismatic and surveyor compass

Applied physics, Write the principle of reversibility of light.

Write the principle of reversibility of light.

Explain the limitations of rebound hammer, Explain the Limitations of Rebou...

Explain the Limitations of Rebound Hammer? The following characteristics of concrete can affect the correlation of the rebound number with the actual surface hardness and shoul

Formation of frost heave, Q. Formation of frost heave? In the past, it ...

Q. Formation of frost heave? In the past, it was believed that formation of frost heave was related to volumetric expansion of soil water which changed from liquid state to sol

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd