Remedial proposal to rectify situation, Civil Engineering

Assignment Help:

Question

During deep excavation, neighbouring ground water table is drawn down that might affect settlement of nearby buildings. What is remedial proposal to rectify situation?


Answer

One of methods to manage settlement of nearby buildings Because of excavation work is by recharging. Water composed in wells in deep excavation is place back to top of excavation in order to raise drawn-down water table. Location of recharge has to be properly selected to ensure soil is adequately permeable to transfer pumped water back near pretentious building.

 

 


Related Discussions:- Remedial proposal to rectify situation

Improvements to public bus transport, Improvements to Public Bus Transport:...

Improvements to Public Bus Transport: Since buses carry a large number of passengers, improvements in bus transport is a cheap solution. Some of the possible improvements are

Shear force and bending moment, how to draw shear force and bending moment ...

how to draw shear force and bending moment from load intensity

What do you mean by settlement cracks, Q. What do you mean by Settlement Cr...

Q. What do you mean by Settlement Cracks? Settlement cracks normally take place in diagonal position. Sometimes vertical cracks may also take place (Figure (a)). Settlement cra

Importance of tendons in post-tensioned members, Importance of Tendons in p...

Importance of Tendons in post-tensioned members Tendons in post-tensioned members are subjected to different amounts of stresses (among themselves) due to following reasons.

Vibration in structures – resilient bearings, Q. Vibration in structures - ...

Q. Vibration in structures - resilient bearings? When railway tunnels are built close to buildings, ground-borne vibration is transmitted to buildingsthrough compression and sh

Explain about catch sidings, Q. Explain about Catch Sidings? Normally a...

Q. Explain about Catch Sidings? Normally all catch sidings except those which are sanded shall be kept alive. On sanded catch siding, the rails shall be kept clear of sand for

How do you maintain water pressure, If you have water pressure and wish to ...

If you have water pressure and wish to handle it, do not cause flow in the line, which will decrease pressure because of friction. To keep pressure up, decrease friction by increas

Calculate the required length of transition, Q  A transition curve is requi...

Q  A transition curve is required for a circular curve of 200-meter Φ radius, the gauge being 1.5 m. and max super elevation restricted to 15 cm. The transition restricted to 15 cm

Afflux in rivers with non scourable bed, Q. Afflux in rivers with non scour...

Q. Afflux in rivers with non scourable bed? Afflux is defined as rise of flood level of the river upstream of a bridge as a result of the obstruction to natural flow caused by

Write short notes on numerical rating of bridges, Q. Write short notes on N...

Q. Write short notes on Numerical rating of Bridges? In the numerical rating system, the condition of a bridge is represented by a number consisting eight digits. This eight di

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd