Reasons for blockage in pumping concrete, Civil Engineering

Assignment Help:

Q. Reasons for blockage in pumping concrete ?

Concrete pumping is normally adopted in highly elevated locations for which access for concrete trucks is difficult. Construction works can be boosted up by using concrete pumping since a larger volume of pours can be achieved within a specified duration when compared with normal concrete placing methods.  

Blockage can take place at the time of pumping operation for the subsequent two common reasons:

(i)  For saturated concrete mixes, pump pressures can force water out of the concrete leading in bleeding. Flow resistance is then increased and can contribute to blockage of pipelines. 

(ii) If cement content (or other components of concrete mixes which increase frictional forces) is high, a higher frictional resistance to pumping can develop and concrete can't be pump able.


Related Discussions:- Reasons for blockage in pumping concrete

N-type semiconductor is an example of what semiconductor, N-type semiconduc...

N-type semiconductor is an example of what semiconductor? Answer : N-type semiconductor is an example of extrinsic semiconductor.

Sewer manhole, minimun difference in level of inlet and oulet pipe level in...

minimun difference in level of inlet and oulet pipe level invert in manhole

Define the transmissivity and reynold number, Define the Transmissivity and...

Define the Transmissivity and Reynold Number TRANSMISSIVITY: (T) A measurement of the rate of groundwater movement through different soil and rock materials. For both confined

Principles and Practices of Management, How Will You Influence People to St...

How Will You Influence People to Strive Willingly for Group Objectives in Your Organization (Target Based Industry)? Apply Your Interpersonal Influence Through Communication Proces

What is a feasibility study, In order to make wise investments in a marketp...

In order to make wise investments in a marketplace experiencing enhancing levels of risk, companies are turning to feasibility studies to verify if they should offer new products,

Hydrographic data for design of bridge, Q.What Hydrographic data required f...

Q.What Hydrographic data required for Design of bridge? (i) Design discharge for bridge waterway and foundation with corresponding high flood levels. Frequency curve for annual

Dams, types of dams

types of dams

Properties a water proofing system, Q- Mention 5 essential properties a wat...

Q- Mention 5 essential properties a water proofing system should have? Ans.- water proofing system should have the following essential properties :- a) It should be im

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd