Q. Reasons for blockage in pumping concrete ?

Concrete pumping is normally adopted in highly elevated locations for which access for concrete trucks is difficult. Construction works can be boosted up by using concrete pumping since a larger volume of pours can be achieved within a specified duration when compared with normal concrete placing methods.  

Blockage can take place at the time of pumping operation for the subsequent two common reasons:

(i)  For saturated concrete mixes, pump pressures can force water out of the concrete leading in bleeding. Flow resistance is then increased and can contribute to blockage of pipelines. 

(ii) If cement content (or other components of concrete mixes which increase frictional forces) is high, a higher frictional resistance to pumping can develop and concrete can't be pump able.


Related Discussions:- Reasons for blockage in pumping concrete

Explain template jig, Explain Template Jig? 1) Template jig is the simp...

Explain Template Jig? 1) Template jig is the simplest type of jig, employed for accuracy than speed. 2) This jig fits over, on, or, into the work and is not generally clampe

Enumerate about the bonded member, Enumerate about the Bonded Member It...

Enumerate about the Bonded Member It is a concrete member in which tendons are bonded to the concrete. They may be directly bonded to the concrete as in the case of pre-tension

Explain the primary treatment for wastewater, Explain the Primary Treatment...

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed

Maximum shear stress, Maximum shear stress: The state of stress at a c...

Maximum shear stress: The state of stress at a critical point of a strained solid is given by σ x = 70 kN/mm 2 , σ y = - 50 kN/mm 2 and τ xy = 45 kN/mm 2 . If the strength

Gas welding be erected in upright position, Question Explain some reaso...

Question Explain some reasons why should acetylene gas cylinders used for gas welding be erected in upright position? Answer Acetylene gas is usually used for gas wel

Lateral load, http://www.expertsmind.com/questions/tributary-lateral-load-3...

http://www.expertsmind.com/questions/tributary-lateral-load-30133097.aspx

Track structure on broad gauge, Q. What is the minimum prescribed track str...

Q. What is the minimum prescribed track structure for LWR / CWR on Broad Gauge? Ans.- 1. General - The minimum length of LWR depends upon - i. Range of temporary variati

Pavement drainage, Pavement Drainage: Water enters the pavement layer...

Pavement Drainage: Water enters the pavement layers through cracks, joints and open spaces in the pavement surface. The water reaches the soil sub-grade on which the pavement

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd