Pre-stressing work, Civil Engineering

Assignment Help:

Under which situation shall engineers use jacking in agreement end only and from both ends in pre-stressing work?


Related Discussions:- Pre-stressing work

What do you mean by manhole loss, Q. What do you mean by Manhole loss? ...

Q. What do you mean by Manhole loss? Manholes are provided in locations where there are changes in direction, size and gradient of gravity pipelines. Generally practice for str

Statics - rigid body of equilibrium, The ball of a trailer hitch is subject...

The ball of a trailer hitch is subjected to a force F. If the failure occurs when the moment of point F around point A reaches 11250 in lbs, determine the largest value F may have

Moment, difference between moment and bending moment

difference between moment and bending moment

Show afflux and scour in alluvial rivers, Q. Show Afflux and scour in alluv...

Q. Show Afflux and scour in alluvial rivers? In case of alluvial rivers, the river bed comprises scourable material like sand. Constriction of bridge waterway causes increase

Graphics, 1. Draw the projections of a line AB that is 50 mm long and is pa...

1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm

Hydraulics, what is hydraulic grid line

what is hydraulic grid line

What is meant by normally consolidated clay stratum, Determine what is mean...

Determine what is meant by normally consolidated clay stratum and over-consolidated clay stratum. Draw typical results of consolidation test data to a suitable plot relating the vo

Working from whole to part, explain the principle of working from whole to ...

explain the principle of working from whole to part, as used in surveying

Harbour layout, Harbour Layout: A harbour has the following constitue...

Harbour Layout: A harbour has the following constituent parts: (a)        An entrance channel, 100-300 m wide (b)       A turning basin, dia 400-600 m (c)        A b

Main problems related with prestressed concrete piles, Question What ar...

Question What are main problems related with prestressed concrete piles ? Answer Origin of Daido piles comes from Japan where these prestressed actual piles are used

12/5/2013 6:27:14 AM

Throughout pre-stressing operation at one end, frictional losses resolve occur and pre-stressing force decreases along a length of tendon until reaching other end. These frictional losses include a friction induced due to change of curvature of tendon duct and also shake effect due to deviation of duct alignment from a centreline. Therefore, pre stress force in the mid-span or at another end would be greatly reduced in case frictional loss is high. Consequently, pre stressing, from both ends for single span for example pre stressing one-half of total tendons at one finish and remaining half at another end is carried out to allow an even distribution and to provide symmetry of pre-stress force along structure.


In actuality, stress at one end only has the potential benefit of lower price when compared with stressing from both ends. For multiple spans as in two spans with not the same span length, jacking is usually approved out at an end of a longer span so to provide a higher pre stress force at location of maximum positive moment. On opposing, jacking from an end of shorter span will be conducted if a negative moment at intermediate support controls pre stress force. However, if total span length is sufficiently long, jacking from the both ends has to be considered.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd