(i) If the fracture is such that, wide gap A T welding ban be adopted, then the total length of fractured ends to-be cut shall be equal to the gap required for wide gap welding. Once the two ends are cut, a gap required for wide gap welding will be created by using rail tensors and joint welded by wide-gap Alumino Thermit welding technique.

ii) In case rail closure Temporary Repairs ( ii ) ( a ) has been provided for temporary repairs one joint of the closure rail shall be welded without rail tenser after setting correct gap for welding. However to ensure correct gap during welding of the other joint, tensor shall be used.

iii) In case rail closure as per Temporary Repairs (ii) (b) has been provided at the time of temporary repairs, the rail closure shall be suitably cut such that the length of the rail to be final inserted in track is equal to length of rail remove from track after fracture minus allowances for two welds i.e. 50 mm. Once the closure rail is cut, the closure rail will be welded.

iv) After welding of joints, a length of track equal to breathing length or about 125 meters on either side be unfastened and tapped to ensure equalisation of stress and then refastened.


Related Discussions:- Permanent repairs to rail fracture

Shear force, Shear distribution for I section

Shear distribution for I section

#title.METALS., WHAT IS THE DIFFERENCE BETWEEN FERROUS AND NON FERROUS META...

WHAT IS THE DIFFERENCE BETWEEN FERROUS AND NON FERROUS METALS

Role of rebate in typical construction joint, Question What is role of reba...

Question What is role of rebate in typical construction joint ? Answer Construction joints are formed on sites to facilitate construction procedure. Though, if improperly constr

Determine the settlement of the foundation, The thiclcness of the normally...

The thiclcness of the normally consolidated soft clay layer is 6 m. The natural water content is 31 percent. The specific gravity of the soil being 2.68 with a liquid limit of 4

Bricks properties, what is the application of silica,aluminaand magnesium i...

what is the application of silica,aluminaand magnesium in bricks?

What is objective method of assessment, Q. What is objective method of asse...

Q. What is objective method of assessment? Track recording consists of objective method of assessment of the quality of track with the help of sophisticated equipments. A conti

Formwork, slabs and beam formwork

slabs and beam formwork

Arches and lintels, classification of arches based on their shape are?

classification of arches based on their shape are?

Write short notes on numerical rating of bridges, Q. Write short notes on N...

Q. Write short notes on Numerical rating of Bridges? In the numerical rating system, the condition of a bridge is represented by a number consisting eight digits. This eight di

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd