Permanent repairs to rail fracture, Civil Engineering

Assignment Help:

Q. Permanent Repairs to rail fracture?

(i) If the fracture is such that, wide gap A T welding ban be adopted, then the total length of fractured ends to-be cut shall be equal to the gap required for wide gap welding. Once the two ends are cut, a gap required for wide gap welding will be created by using rail tensors and joint welded by wide-gap Alumino Thermit welding technique.

ii) In case rail closure Temporary Repairs ( ii ) ( a ) has been provided for temporary repairs one joint of the closure rail shall be welded without rail tenser after setting correct gap for welding. However to ensure correct gap during welding of the other joint, tensor shall be used.

iii) In case rail closure as per Temporary Repairs (ii) (b) has been provided at the time of temporary repairs, the rail closure shall be suitably cut such that the length of the rail to be final inserted in track is equal to length of rail remove from track after fracture minus allowances for two welds i.e. 50 mm. Once the closure rail is cut, the closure rail will be welded.

iv) After welding of joints, a length of track equal to breathing length or about 125 meters on either side be unfastened and tapped to ensure equalisation of stress and then refastened.


Related Discussions:- Permanent repairs to rail fracture

Illustrate the design discharge for foundation, Q. Illustrate the Design di...

Q. Illustrate the Design discharge for foundation? To provide for an adequate margin of safety, the foundation and protective works of a bridge should be designed for a flood d

Traditional granular sub-base, Question For rigid pavement, what is rec...

Question For rigid pavement, what is recompense of using lean concrete sub-base instead of traditional granular sub-base? Answer There are some shortcomings of using

Reinforced Concrete Design, design a 3-meter cantilever slab to carry a uni...

design a 3-meter cantilever slab to carry a uniform total dead load of 8.2KN/m^2 and a concentrated live load at the free end of 30 KN/m. f''c=28Mpa fy=420Mpa.

Water absorption test for precast concrete pipes, Purpose of carrying out w...

Purpose of carrying out water absorption test for precast concrete pipes Cement will mix with more water than is essential to ultimately combine during hydration of cement pas

Evaluate break even point, Evaluate break even point: A vehicle manufa...

Evaluate break even point: A vehicle manufacturing firm purchase axle from a shaft manufacturing industry at Rs.100 each. If it establishes the essential apparatus for the pro

Calculate the energy loss in the piping system, The head (energy) loss in t...

The head (energy) loss in the piping system between points 1 and 7 is the most nearly. Solution: 3 ft. The difference between point 1 and point 7 = 10 ƒt - 7 ƒt = 3 ƒt

Explain the term - uniaxial - biaxial -triaxial prestressing, Explain the t...

Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di

Verify the total active thrust on the wall per lineal metre, A smooth backe...

A smooth backed vertical wall is 6.3 m high and retains a soil with a bulk unit weight of 18 kN/m 3 and φ = 18°. The top of the soil is level with the top of the wall and is horiz

Soil in road construction, Soil in Road Construction: Road Embankme...

Soil in Road Construction: Road Embankment and Sub-grade Soil is mainly used as the material for constructing a road embankment. The road embankment supports the road

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd