A brilliant UTM student at the end of his graduation is in presence of two opportunities and has to choose between them. One is a job offer with a salary of Rs15,000 per month (with no other benefits except for one month end of year bonus). It is expected that the monthly salary will increase on average by 10% every year for the first 5 years of his career. His personal costs amount to Rs5,000 per month and is expected to increase by 5% every year for the next 5 years. The next opportunity is the possibility of creating his own call centre which promises the following benefits: a steady revenue stream of Rs100,000 per month with an increase of 30% every year.

Operational costs for the call centre are about Rs65,000 per month and will increase by 10% each year for the first 5 years. It is assumed that an investment of Rs500,000 will be required in the second case which will be granted as an interest free loan by the Government with annual repayments of Rs100,000 over the next 5 years.

(a) Summarise the net cash flows for each opportunity for a period of 5 years. For simplification purposes, ignore the effect of taxes (both corporate and income tax).

(b) Calculate the Net Present Value for each opportunity. Use 10% as discount rate.

(c) Which opportunity is better from the financial point of view?

Related Discussions:- NPV

Motivation fectore at work, ye project topic kis web site pr hai jise downl...

ye project topic kis web site pr hai jise downlode kar sake

Ask question #MCORWTN CORPORATION Questions, 10. How should West have handl...

10. How should West have handled the situation where Pat Ray''s opinion of the test data was contrary to that of Corwin''s engineering personnel? 1 1. How should West have reacted

Explain the methodology of sequencing the activities, Question 1 For a...

Question 1 For an event manager, organizing an AGM would be a relatively 'dry' affair as the elements of entertainment, decoration and catering are missing in this event (some

Quantitative layout analysis - Trial and Error Method, Quantitative layout ...

Quantitative layout analysis - Trial and Error Method Here we use simple travel chart and graphical approach to reduce to minimize nonadjacent flows by centrally locating the

., discussthe nine project management knowledge areas

discussthe nine project management knowledge areas

What is project management methodology, Question 1: (a) What is project...

Question 1: (a) What is project management methodology ? (b) Why do you say that project management is the best method of implementing change ? Question 2: (a)

Strategic project assignment, #question your team has been retained to help...

#question your team has been retained to help the company launch it''s products into the global marketplaace. each team is assigned to investigate one country market. The primary o

Stakeholder management, 3. What are some ways to manage a stakeholder rela...

3. What are some ways to manage a stakeholder relationship closely? Give examples of how you might manage relationships differently based on the unique personalities of different

Demonstrate a critical approach to management theories, Your Integrated Man...

Your Integrated Management Project will be marked initially by a tutor. The marked project may then moderated by another tutor to ensure consistency between markers. A sample of th

Precedence Diagrams, I know how to construct a precedence diagram but i am ...

I know how to construct a precedence diagram but i am asked the question :use the largest candidate rule to assign work elements to stations using a service time of 1.5 min how do

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd