Moisture-density relationship, Civil Engineering

Assignment Help:

Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Optimum binder content in bituminous pavement, Q. Optimum binder content in...

Q. Optimum binder content in bituminous pavement? Amount of binder to be added to a bituminous mixture can't be too excessive or too little. Principle of designing the optimum

Levelling, how to go about the collimation method.

how to go about the collimation method.

Equipments required for under water inspection of bridge, Define Equipments...

Define Equipments and tools required for under water Inspection of Bridge? Since the underwater inspection of stone masonry substructures involve only a cursory inspection of t

Explain the statements about construction contract process, Explain the Sta...

Explain the Statements about the Construction Contract Process I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is

Levelling, difference between fly levelling and differential levelling

difference between fly levelling and differential levelling

Masonry, Sketches for English bond, Stretcher bond, Header bond, Flemish bo...

Sketches for English bond, Stretcher bond, Header bond, Flemish bond in first & second layer plan, elevation and 3 dimensional view of brick bond.

How do you measure concrete, We can measure concrete by Cubic feet, Cubic y...

We can measure concrete by Cubic feet, Cubic yards, Cubic Meter

Define the alternate depths - hydrologic system, Define the Alternate Depth...

Define the Alternate Depths In open channels, two alternate depths of flow have the same energy for the same flow rate. As shown in the figure, the hyperbolic plot of energy (x

Loading and unloading cycles for soil nails, In carrying out pull-out tests...

In carrying out pull-out tests for soil nails, it generally requires the unloading and loading of soil nails of several cycles up to 80% of ultimate tensile strength of soil nails.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd