Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Describe the geophysical profileof borings, Describe the Geophysical Profil...

Describe the Geophysical Profileof Borings The variation in the thickness of the soil stratum for engineering application is known as the geophysical profile. Figure 1.2 shows

Define reactivity - hazardous waste, Define Reactivity - Hazardous Waste ...

Define Reactivity - Hazardous Waste - Undergoes violent Change w/o detonating - reacts violently with water - Forms potentially explosive mixtures with water - generat

Harbour layout, Harbour Layout: A harbour has the following constitue...

Harbour Layout: A harbour has the following constituent parts: (a)        An entrance channel, 100-300 m wide (b)       A turning basin, dia 400-600 m (c)        A b

Compression members, Compression Members: Compression members in steel...

Compression Members: Compression members in steel need special care in design. Steel possesses high strength in tension/compression; hence the sections are generally small com

Function of a separation membrane amid concrete pavement, Question What...

Question What is main function of a separation membrane amid concrete pavement slab and sub-base ? Answer Division membrane between concrete pavement slab and sub-bas

Trigo, a pilot entering a bay on course

a pilot entering a bay on course

#titlecivil war.., how can you know that the civil war real.

how can you know that the civil war real.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd