Minimum and maximum area of reinforcement, Civil Engineering

Assignment Help:

Q. Minimum and maximum area of reinforcement?

Minimum area of reinforcement vs. maximum area of reinforcement

Beams can be designed to be larger than required for strengthconsideration because of aesthetics or other reasons. As such, corresponding steel ratio is very low and moment capacity of pure concrete section based on the modulus of rupture is higher than its ultimate moment of resistance. Consequently reinforcement yields first and extremely wide cracks will be formed. A smallest area of reinforcement is specified to avoid the formation of wide cracks.

Contrariwise, a maximum area of reinforcement is specified to allow the placing and compaction of fresh concrete to occur easily.


Related Discussions:- Minimum and maximum area of reinforcement

Cleaning and greasing of steel sliding bearings, Cleaning and greasing of s...

Cleaning and greasing of steel sliding bearings : Following equipments are required for greasing of steel sliding bearings: 1. Jacks (50 ton capacity) - 2 nos. 2. Hard wo

Explain precedence relationships - construction management, Explain the Pre...

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish

Beam stress, what is the bending stress for a simply supported beam with th...

what is the bending stress for a simply supported beam with three equal concentrated loads that are equally spaced?

What do you mean by stock verification sheets, Q. What do you mean by Stock...

Q. What do you mean by Stock Verification Sheets? The proper custody and accountal of stores is the prime duty and function of an executive or the stockholder. To ensure this v

Design a 10 unit rapid sand filter system, Design a 10 unit rapid sand filt...

Design a 10 unit rapid sand filter system for a flow of 6.3 MGD with a filtration rate of 2 gpm/sq ft. and an L: W ratio of 1.3.   Design flow (Q) = 6.3 MGD = 6.3x106 gpd =

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Consolidation settlement, The integration of strain over the depth is settl...

The integration of strain over the depth is settlement. The method of producing the settlement is non-recoverable when the intensity of stress is removed. Hence, a permanent reduc

Direct levelling, to find height difference between two or more points in d...

to find height difference between two or more points in different conditions

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd