Q. Minimum and maximum area of reinforcement?

Minimum area of reinforcement vs. maximum area of reinforcement

Beams can be designed to be larger than required for strengthconsideration because of aesthetics or other reasons. As such, corresponding steel ratio is very low and moment capacity of pure concrete section based on the modulus of rupture is higher than its ultimate moment of resistance. Consequently reinforcement yields first and extremely wide cracks will be formed. A smallest area of reinforcement is specified to avoid the formation of wide cracks.

Contrariwise, a maximum area of reinforcement is specified to allow the placing and compaction of fresh concrete to occur easily.


Related Discussions:- Minimum and maximum area of reinforcement

Disparities b/w epoxy grout cement grout and cement mortar, Question What a...

Question What are the key disparities between epoxy grout cement grout and cement mortar ? Answer Epoxy grout contains of epoxy resin, epoxy hardener and sand or aggregates.

Properties of matter, Properties of Matter: Due to surface tension,...

Properties of Matter: Due to surface tension, the free surface of a liquid behaves like a stretched elastic membrane tending to contract so as to have minimum surface area.

Plane table sureying, discuss the resection method of plane table sureying ...

discuss the resection method of plane table sureying in detail

Stones, what are the different type of stones?

what are the different type of stones?

Forces reactions at that point, Mad/Sir What would be the Horizontal and ve...

Mad/Sir What would be the Horizontal and vertical component from this acting force see diagram

Survey, relationship between included angles and whole circle bearing

relationship between included angles and whole circle bearing

Major dissimilarity between standpipe, Question What is major dissimila...

Question What is major dissimilarity between standpipe, standpipe piezometer and piezometer ? Answer Standpipe usually contains plastic pipes with punctured holes at

Wet mix Macadam, Test required before laying or after laying.

Test required before laying or after laying.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd