Method of construction of a bored cast-in-situ concrete pile, Civil Engineering

Assignment Help:

Q. Method of construction of a bored cast-in-situ concrete pile?

Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole and is driven with the help of a bailer. Further boring below this casing is carried out by chiselling and the side walls are kept stable by circulating bentonite slurry inside the bore hole. The Bentonite clay used in the operation should conform to provisions made in IS : 2911 -Part -1, section -2. After reaching the founding level, the chisel is removed, the bore hole flushed and the reinforcement cage lowered into the hole and held in position by tack welding it to the support bars at the top of the casing.

After this the concreting is carried out by using a "tremie" .The concreting is continued till a good quality concrete is seen at the top of the bore hole. The concrete used is a high slump mix (not leaner than M 20 grade ). Cast-in-situ piles in which the steel shell is left in the ground ensures the quality of concrete and offers corrosion protection in soils containing chlorides and sulphates.

635_Method of construction of a bored cast-in-situ concrete pile.png


Related Discussions:- Method of construction of a bored cast-in-situ concrete pile

Asdasd, #questiasdasdasdasdon..

#questiasdasdasdasdon..

Types of limes and their properties, Types of Limes and their Properties ...

Types of Limes and their Properties The limes are classified in three categories as fat lime, hydraulic lime and poor lime: (1) Fat lime: It is composed of 95 percentage o

How to calculate the coefficient of permeability, The discharge of water co...

The discharge of water collected from a constant head permeameter in a period of 15 minutes is 500 ml. The internal diameter of the permeameter is 5 cm and the measured difference

Define channel jig, Define Channel Jig a) A channel jig is the simplest...

Define Channel Jig a) A channel jig is the simplest form of box jig. b) The work is placed in a channel shaped trough and clamped by mean of screw. c) It is utilized

Radial flow pumps for small flows and high heads, Radial flow pumps for sma...

Radial flow pumps for small flows and high heads In radial flow pumps, a diffuser/volute is generally designed at it outlet to convert the kinetic energy obtained during the pu

What is the correct value of the specific gravity, In a specific gravity te...

In a specific gravity test, 1.17 N of oven-dired soil was taken. The weight of pyknometer, soil and water was obtained as 6.51 N. The weight of pyknometer full of water alone was 5

Continuous flow systems, Continuous Flow Systems: Transport by road, r...

Continuous Flow Systems: Transport by road, rail, air or ships takes place in vehicles which move along a path at intervals. As against this, continuous flow systems are those

Construction of embankment, Construction of Embankment: The following...

Construction of Embankment: The following steps describe embankment construction : (a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed

Designing of watermain, Question In designing of watermain , regular p...

Question In designing of watermain , regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than 600mm. Give some speci

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd