Q. Method of construction of a bored cast-in-situ concrete pile?

Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole and is driven with the help of a bailer. Further boring below this casing is carried out by chiselling and the side walls are kept stable by circulating bentonite slurry inside the bore hole. The Bentonite clay used in the operation should conform to provisions made in IS : 2911 -Part -1, section -2. After reaching the founding level, the chisel is removed, the bore hole flushed and the reinforcement cage lowered into the hole and held in position by tack welding it to the support bars at the top of the casing.

After this the concreting is carried out by using a "tremie" .The concreting is continued till a good quality concrete is seen at the top of the bore hole. The concrete used is a high slump mix (not leaner than M 20 grade ). Cast-in-situ piles in which the steel shell is left in the ground ensures the quality of concrete and offers corrosion protection in soils containing chlorides and sulphates.

635_Method of construction of a bored cast-in-situ concrete pile.png


Related Discussions:- Method of construction of a bored cast-in-situ concrete pile

Trigo, a pilot entering a bay on course

a pilot entering a bay on course

Principle of adding cooling pipes, Question What is key principle of a...

Question What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation? Answer These methods aim at reducing placing tem

Physics, about lenses & mirrors for assignment

about lenses & mirrors for assignment

Define inspection of pier or abutment, Define Inspection of Pier or Abutmen...

Define Inspection of Pier or Abutment? Inspection of pier/abutment may then be carried out as under: i. Conduct visual inspection of the entire surface using up and down swe

Calculate the square foot of contact area for the formwork, A concrete crew...

A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square

Local scour at obstructions in rivers, Q. Local Scour at obstructions in ri...

Q. Local Scour at obstructions in rivers? When the water flow in river is deflected by obstructions such as bridge piers, scouring would occur arising from formation of vortexe

Water absorption test for precast concrete pipes, Purpose of carrying out w...

Purpose of carrying out water absorption test for precast concrete pipes Cement will mix with more water than is essential to ultimately combine during hydration of cement pas

Diffrence between rowe cell and oedometer apparatus, Q. Diffrence between R...

Q. Diffrence between Rowe cell and Oedometer apparatus? The benefits of using Rowe cell over oedometer apparatus are:  (i)  It possesses control facilities for drainage and

Show the functions of diaphragm walls, Q. Show the Functions of diaphragm w...

Q. Show the Functions of diaphragm walls? The functions of diaphragm walls are as follows: (i)  It is designed to maintain soils during the construction of underground

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd