Q. Method of construction of a bored cast-in-situ concrete pile?

Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole and is driven with the help of a bailer. Further boring below this casing is carried out by chiselling and the side walls are kept stable by circulating bentonite slurry inside the bore hole. The Bentonite clay used in the operation should conform to provisions made in IS : 2911 -Part -1, section -2. After reaching the founding level, the chisel is removed, the bore hole flushed and the reinforcement cage lowered into the hole and held in position by tack welding it to the support bars at the top of the casing.

After this the concreting is carried out by using a "tremie" .The concreting is continued till a good quality concrete is seen at the top of the bore hole. The concrete used is a high slump mix (not leaner than M 20 grade ). Cast-in-situ piles in which the steel shell is left in the ground ensures the quality of concrete and offers corrosion protection in soils containing chlorides and sulphates.

635_Method of construction of a bored cast-in-situ concrete pile.png


Related Discussions:- Method of construction of a bored cast-in-situ concrete pile

What is the station at point b, What is the station at Point B? SO...

What is the station at Point B? SOLUTION 3 Station at Point A = Sta 22+45  Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273'  = Sta 32+73

Boundaries of rational method in calculating runoff, Question What are main...

Question What are main boundaries of Rational Method in calculating runoff? Answer Calculation of runoff is compound matter that depends on a lot of factors similar to ground

Define the term - post-tensioned concret, Define the term - post-tensioned ...

Define the term - post-tensioned concret In the Prescon and B.B.R.V. systems button heads are created at the ends of tendons. In the case of Prescon system, 2 to 130 tendon wir

Elongation, Elongation of bar due to self weight

Elongation of bar due to self weight

Engineering indicators in case of multi speed restriction, Multi Speed Rest...

Multi Speed Restriction (i.e. existence of two or more than two speed restrictions in continuation) When work of deep screening or sleeper renewal is in progress, there is situ

Explain situations that warrant a damage inspection, Explain Situations tha...

Explain Situations that warrant a damage inspection? - Floods - bridges located in streams, rivers and other waterways with known or suspected scour potential. - Build-up of

Engineering Science, 1(a)Explain the difference between a concurrent and a ...

1(a)Explain the difference between a concurrent and a non concurrent force system . (b)If a non coplanar force system is acted upon by equal and opposite forces,it must be in equil

What do by diaphragm wall, Q. What do by Diaphragm wall? For the constr...

Q. What do by Diaphragm wall? For the construction of diaphragm walls adjacent to buildings, former experience showed that excess slurry head above groundwater level had to be

Surveying, Explain about reciprocal ranging

Explain about reciprocal ranging

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd