Method of construction of a bored cast-in-situ concrete pile, Civil Engineering

Assignment Help:

Q. Method of construction of a bored cast-in-situ concrete pile?

Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole and is driven with the help of a bailer. Further boring below this casing is carried out by chiselling and the side walls are kept stable by circulating bentonite slurry inside the bore hole. The Bentonite clay used in the operation should conform to provisions made in IS : 2911 -Part -1, section -2. After reaching the founding level, the chisel is removed, the bore hole flushed and the reinforcement cage lowered into the hole and held in position by tack welding it to the support bars at the top of the casing.

After this the concreting is carried out by using a "tremie" .The concreting is continued till a good quality concrete is seen at the top of the bore hole. The concrete used is a high slump mix (not leaner than M 20 grade ). Cast-in-situ piles in which the steel shell is left in the ground ensures the quality of concrete and offers corrosion protection in soils containing chlorides and sulphates.

635_Method of construction of a bored cast-in-situ concrete pile.png


Related Discussions:- Method of construction of a bored cast-in-situ concrete pile

Open foundation, what is savest foundation in the soft sanded earth

what is savest foundation in the soft sanded earth

Angle measurment, calculating included angle and bearing

calculating included angle and bearing

Soil testing, what is black cotton soil in dry condition

what is black cotton soil in dry condition

Engineering mathamatics, #question.A strain gauge arrangement is used to me...

#question.A strain gauge arrangement is used to measure the applied force of a comnplex shaped civil engineering structure. Theoretical analysis have been round the relationship be

Arches and lintels, classification of arches based on their shape are?

classification of arches based on their shape are?

Proctor test for GSB material, what is the procedure for gsb proctor test f...

what is the procedure for gsb proctor test for matrial sampling for lab density

Vertical curves - geometric design of roads, Vertical Curves: When tw...

Vertical Curves: When two vertical gradients meet, it is necessary to provide a vertical curve. Two types of vertical curves are used: (a) Summit curve, where the point of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd