Q. Method of construction of a bored cast-in-situ concrete pile?
Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole and is driven with the help of a bailer. Further boring below this casing is carried out by chiselling and the side walls are kept stable by circulating bentonite slurry inside the bore hole. The Bentonite clay used in the operation should conform to provisions made in IS : 2911 -Part -1, section -2. After reaching the founding level, the chisel is removed, the bore hole flushed and the reinforcement cage lowered into the hole and held in position by tack welding it to the support bars at the top of the casing.
After this the concreting is carried out by using a "tremie" .The concreting is continued till a good quality concrete is seen at the top of the bore hole. The concrete used is a high slump mix (not leaner than M 20 grade ). Cast-in-situ piles in which the steel shell is left in the ground ensures the quality of concrete and offers corrosion protection in soils containing chlorides and sulphates.
distomat
what is the design of syphon
how to convert UVL to UDL
what is the errors faced in leveling servey
Briefly explain the difference between compaction and consolidation of soil. What is the effect of compaction on soil properties? Ans.- Compaction - The process of increas
The cost of utilities, taxes and maintenance on a home is $3,000 per year. The amount of money that would have to be invested now at 8% to cover these expenses for the next 5 year
What is DBM?Why use DBM where other binder courses are available?What is composition and advantages of using DBM?
The data profile as shown in Figure is obtained. A best average of N values gave N 10 = 21, column loads including dead and live loads ranged from 500 kN to 950 kN. Determine the
Q. What do you mean by M A S Accounts? This stands for material at site account. This is a suspense head of account that is maintained to watch actual consumption of materials
Question What are the main drawbacks of curing by ponding and polythene sheets ? Answer Purpose of curing is to decrease the speed of heat loss of freshly placed concrete to atm
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd