Mechanical design 2, engineering, Other Engineering

Assignment Help:
Mechanical Design (48650) – Spring Semester 2012
Optimisation Assignment – BUILDING A ROAD
Teams of THREE to FIVE [3 to 5] – Worth 20% of the Semester Grade
Due: Thursday 23rd March 2012 by 23:59 pm
Where? My Assignment Box [No 15] situated in Building 2 between Floors 5 & 6 below the big computer lab on level 6. This is the only way to submit – it eliminates confusion.
Late submissions (without prior permission) will be penalised at -10% per day late. Submissions more than one week late will not be accepted.
Students organise themselves into teams; share out the work; plan a timetable with delivery dates; hold regular face to face meetings and issue minutes, and; show fellow team members how to do things. Acknowledge outside assistance from other students in the report.
1. Background
The cost of building a road depends upon many things. For the purposes of this assignment it will depend on total distance covered and quantity of material cut from a hill, the quantity of material to fill hollows and the net amount of excess earth trucked to/from the area to make up for that used internally. The area being considered covers the coordinates from x = -5 to x = +5 kilometres and from y = +5 to y = -5 kilometres. The height of a point (z in metres) within the area is found from the equation:
z = sin [(x-y2)?/14] + sin [(2x+y)?/9)] - 0.37 {illustrated in the contour map below}
Five pairs of roads can start from the West at x=-5 and y =+4, +2, 0, -2 and -4 always travelling eastward. The pair starting at y = +4 finish at y = 1 and y = -1: the pair starting at y = +2 finish at y = +5 and y = -2: the pair starting at y = 0 finish at y = -3 and y = +3: the pair starting at y = -2 finish at y = -5 and y = +1, and: the pair starting at y = -4 finish at y = +1 and -1. The roads run horizontally at z = zero metres.
The costs (in units of $100,000) are:
Road construction cost is 7/km Cost to fill a hollow is 3/km.metre
Cost to cut into a hill is 2/km.metre. Cost to truck net excess earth to/from the area is 3.5/km.metre
The cut or fill for each step is zav . ?s, where zav = (zleft + 2zmid + zright)/4 and ?s is the step road length.
2. Teams
Teams of three start at x = -5 and y = +4, 0 and -4. Teams of 4 start at x = -5 and y = +4, +2, 0 and -2. Teams of five will start at x = -5 and y =+4, +2, 0, -2 and -4. Each team member will do 2 roads starting at one point and a team will cover all roads allocated to them.
3. The Task
3.1 Maps: Produce a contour map better than that shown below and also a three-dimensional surface graph of the ground. Divide the x and y ranges into steps of 0.25 km.
[Hint; Look up the “range” naming function in “Help” – it allows you to easily write a general formula that can be written to any cell to calculate z and it will automatically step through the x- and y-ranges.]
3.2 Optimisation: Using an optimisation package such as “Solver” in Excel, determine the road path which gives the minimum cost for each starting and finishing point examined by the team. Plot the road route and z-elevation profile for each road. A small bonus will be awarded for the team with the lowest cost, viable solution.
[Hints: Move from x = -5 to x = +5 in steps of 0.5 km [or 0.25 km, preferably]. Determine the (i) the road distance for the step and it’s cost; (ii) the z at the half x-step co-ordinates; (iii) the “fill” or “cut” for that step; (iv) the cost of the fill or cut for that step; (v) the net fill or cut for the road and it’s cost; (vi) the total road cost, and; (vii) optimise the y-path to minimise total cost. Check for correct operation by putting all costs except road construction to zero – you should get a straight line road path. Warning! Try several initial path guesses to get the “best” path. “Play’ with the option settings in Solver.]

Related Discussions:- Mechanical design 2, engineering

Difference amplifier, Difference amplifier: Figure shows how two inputs...

Difference amplifier: Figure shows how two inputs can be subtracted. This circuit differs from previous types with negative feedback in that the non-inverting terminal is not

DSP, bit reversed process 10 point dft

bit reversed process 10 point dft

Amplifiers, simplied hybrid model of cc amplifier

simplied hybrid model of cc amplifier

Weighted average cost of capital, Using this link and the information there...

Using this link and the information therein ( http://www.sec.gov/Archives/edgar/data/1110452/000119312507151600/d20f.htm#tx19738_13.) find Air France’s weighted average cost of ca

Design a pavilion , i need somone to design a pavilion for me

i need somone to design a pavilion for me

Java , why we need EJB

why we need EJB

Jupiter and saturn, Expertsmind.com  brings you unique solution in Electri...

Expertsmind.com  brings you unique solution in Electrical Engineering -           Jupiter and Saturn are made almost entirely of hydrogen and helium with

Engineering mechanics questions, I need help in engineering mechanics quest...

I need help in engineering mechanics questions? Do you provide homework help, Please let us know how do i get it quich time...

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd