What are main functions of slip joints in block work seawalls?


Answer

Slip joints are joints that are formed during a complete vertical plane from cope level to toe level of seawalls. These joints are intended in mass work seawalls to cater for likely differential settlements between neighbouring panels of seawalls. Aggregates inside half-round channels in slip joints let for vertical movements induced by differential resolution and at similar time providing collective interlocking forces among neighbouring panels of seawalls to link panels in one component against lateral earth pressure used on seawall.

 


Related Discussions:- Main functions of slip joints in block work seawalls

Traverse, how to fill traverse computation sheet of opened traversig ..

how to fill traverse computation sheet of opened traversig ..

Local vehicle parapet strong enough to contain vehicles, Q. Local vehicle p...

Q. Local vehicle parapet strong enough to contain vehicles? Majority of local parapets are 1.1m high in addition they are designed to resist impact from a 1.5ton car moving at

Define resultant force on a given area of a horizontal plane, Resultant For...

Resultant Force on a Given Area of a Horizontal Plane By equation, the total vertical force applied to an area A on the plane is: Resultant Force R = ΡA = (lb/ft 2 )(ft 2 )

Commercial building, i) Describe the general significant of energy performa...

i) Describe the general significant of energy performance in industrial or commercial buildings.  ii) Draw the building layout and produce an overall description that will have

Effect of concrete placing temperature, Effect of concrete placing temperat...

Effect of concrete placing temperature on early thermal movement Rate of hydration of cement paste is related to placing temperature of concrete. Rate of heat production is giv

Premix carpet - road pavements, Premix Carpet: An open graded premix ...

Premix Carpet: An open graded premix carpet, commonly called premix carpet (PC), is an open graded premixed material laid to a thickness of 20 mm and rolled, followed by a se

Assignment., classification and characterstics of lintels

classification and characterstics of lintels

LEVELLING, WHAT IS FLYBBACK LEVELLING

WHAT IS FLYBBACK LEVELLING

What is chamfering of rail, Q. What is Chamfering of rail? Chamfering o...

Q. What is Chamfering of rail? Chamfering of rail holes has been done for the life of rail hole is increased and chances of the rail hole developing any crack is eliminated.

#title.long span truss design, what are the step by step process of designi...

what are the step by step process of designing steel long span trusses?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd