A paper mill produces two grades of paper viz., X and Y. Because of raw
material restrictions, it cannot produce more than 400 tons of grade X paper
and 300 tons of grade Y paper in a week. There are 160 production hours in a
week. It requires 0.20 and 0.40 hours to produce a ton of grade X and Y papers.
The mill earns a profit of Rs. 200 and Rs. 500 per ton of grade X and Y paper
respectively. Formulate this as a Linear Programming Problem.

Related Discussions:- Linear Programming

Scope, Scope of operation research?

Scope of operation research?

Equation, A paper mill produces two grades of paper viz., X and Y. Because ...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Linear Programming Problem, A paper mill produces two grades of paper viz.,...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Determine capacity of unit, Show simple vapour compression Refrigeration cy...

Show simple vapour compression Refrigeration cycle with showing all the devices and also draw T-sand P-R diagram and illustrate it also. A Bell-Coleman cycle works between 1 bar

Critical evaluation of research, 1. What is the major problem or issue bein...

1. What is the major problem or issue being investigated? The interaction between service failure and online shop's readiness for service recovery and the resulting impact on custo

Steps of field study, Festinger and Katz have described followings six ste...

Festinger and Katz have described followings six steps in the conduct to a field study. a. Preliminary Planning :Deciding scope and objectives of study and the time table

Decision analysis, a question was given but i cannot identify the alternati...

a question was given but i cannot identify the alternatives and i do not know how to calculate the right amount of payoff.what are the right ways to calculate the payoff table.

Waiting queques, During busy times, 60 potential customers per hour arrive ...

During busy times, 60 potential customers per hour arrive at the booth (assume a Poisson distribution). A booth worker takes 5 minutes, on average, to meet the information needs of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd