Davidson construction company is building a luxury lakefront home in batangas coordination of the architech an sub contractors will require a major effort to meet the 44-week (approximately 10-month completion date requested by the owner. the Davidson project manager prepared the following information.

A none 4 8 12
B A 6 7 8
C A 6 12 18
D A 3 5 7

Related Discussions:- Quantitative Technique for business

#title. solution, Solve the following Linear Programming Problem using Simp...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2

Decide upon the objective , Decide upon  the Objective  What is it...

Decide upon  the Objective  What is it that you  aim to  achieve  the end  of the  presentation ? your  objective  should  be crystal  clear. Do  not stray or move  a ways

What are the functions of a store manager, Question 1 Explain Pre-Store op...

Question 1 Explain Pre-Store opening activities and State at least 10 pre-store opening activities that should be ideally carried out in a retail store? Question 2 What ar

Operation research, Discuss the methodology of operation research

Discuss the methodology of operation research

Banking operations, sir plz suggest me any book for this...or notes.....

sir plz suggest me any book for this...or notes.....

LINEAR PROGRAMMING, b. A paper mill produces two grades of paper viz., X an...

b. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Optimal assingment, words each) Q2. Six Operators are to be assigned to fiv...

words each) Q2. Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will ha

LPP, . A paper mill produces two grades of paper viz., X and Y. Because of ...

. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper

LPP, USE SIMPLE METHOD TO SOLVE THE FOLLOWING LPP MAXIMISE Z=4X1+10X2 SUBJE...

USE SIMPLE METHOD TO SOLVE THE FOLLOWING LPP MAXIMISE Z=4X1+10X2 SUBJECT TO CONSTRAINS, 2X1+X2 2X1+5X2 2X1+3X2 X1, X2>0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd