Kruskals algorithm, Data Structure & Algorithms

Assignment Help:

Krushkal's algorithm uses the concept of forest of trees. At first the forest contains n single node trees (and no edges). At each of the step, we add on one (the cheapest one) edge so that it links two trees together. If it makes a cycle, simply it would mean that it links two nodes that were connected already. So, we reject it.

The steps in Kruskal's Algorithm are as:

1.   The forest is constructed through the graph G - along each node as a separate tree in the forest.

2.   The edges are placed within a priority queue.

3.   Do till we have added n-1 edges to the graph,

  I.   Extract the lowest cost edge from the queue.

 II.   If it makes a cycle, then a link already exists among the concerned nodes. So reject it.

 III.  Otherwise add it to the forest. Adding it to the forest will join two trees together.

The forest of trees is a division of the original set of nodes. At first all the trees have exactly one node in them. As the algorithm progresses, we make a union of two of the trees (sub-sets), until the partition has only one sub-set containing all the nodes eventually.

Let us see the sequence of operations to determine the Minimum Cost Spanning Tree(MST) in a graph via Kruskal's algorithm. Suppose the graph of graph shown in figure  and below figure  illustrates the construction of MST of graph of Figure

1339_Kruskals Algorithm.png

Figure: A Graph

Figure: Construction of Minimum Cost Spanning Tree for the Graph by application of Kruskal's algorithm

The following are several steps in the construction of MST for the graph of Figure via Kruskal's algorithm.

Step 1 :  The lowest cost edge is chosen from the graph that is not in MST (initially MST is empty). The cheapest edge is 3 that is added to the MST (illustrated in bold edges)

Step 2: The next cheap edge which is not in MST is added (edge with cost 4).

Step 3 : The next lowest cost edge that is not in MST is added (edge with cost 6).

 Step 4 : The next lowest cost edge that is not in MST is added (edge with cost 7).

Step 5 : The next lowest cost edge that is not in MST is 8 but form a cycle. Hence, it is discarded. The next lowest cost edge 9 is added. Now the MST has all the vertices of the graph. This results in the MST of the original graph.


Related Discussions:- Kruskals algorithm

Define big oh notation, Big oh notation (O) : The upper bound for the funct...

Big oh notation (O) : The upper bound for the function 'f' is given by the big oh notation (O). Considering 'g' to be a function from the non-negative integers to the positive real

Explain threaded binary tree, Threaded Binary Tree : If a node in a bin...

Threaded Binary Tree : If a node in a binary tree is not having left or right child or it is a leaf node then that absence of child node is shown by the null pointers. The spac

Define complete binary tree, Define Complete Binary Tree Complete Binar...

Define Complete Binary Tree Complete Binary Tree:- A whole binary tree of depth d is that strictly binary tree all of whose leaves are at level D.

Estimate the probability that the noncritical path , An advertising project...

An advertising project manager developed the network diagram shown below for a new advertising campagign.  In addition, the manager gathered the time information for each activity,

Algorithms & flowchart, write an algorithm to find the average number of oc...

write an algorithm to find the average number of occurances of MECHANIL in an english passage

What are the example of area subdivision method, Example of Area Subdivisio...

Example of Area Subdivision Method The procedure will be explained with respect to an illustrative problem, with the image consisting of five objects, namely a triangle (T), qu

Graphs, floyd warshall algorithm

floyd warshall algorithm

Algorithm, Algorithm to find sum of square of a number

Algorithm to find sum of square of a number

Advantages of first in first out method, Advantages of First in First out (...

Advantages of First in First out (FIFO) Costing Advantages claimed for first in first  out (FIFO)  costing method are: 1. Materials used are drawn from the cost record in

#input restricted DEQUE, #why all the 4 operations i.e. insertion n del...

#why all the 4 operations i.e. insertion n deletion from rear end and front end is valid in input restricted DEQUE

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd