Kruskals algorithm, Data Structure & Algorithms

Assignment Help:

Krushkal's algorithm uses the concept of forest of trees. At first the forest contains n single node trees (and no edges). At each of the step, we add on one (the cheapest one) edge so that it links two trees together. If it makes a cycle, simply it would mean that it links two nodes that were connected already. So, we reject it.

The steps in Kruskal's Algorithm are as:

1.   The forest is constructed through the graph G - along each node as a separate tree in the forest.

2.   The edges are placed within a priority queue.

3.   Do till we have added n-1 edges to the graph,

  I.   Extract the lowest cost edge from the queue.

 II.   If it makes a cycle, then a link already exists among the concerned nodes. So reject it.

 III.  Otherwise add it to the forest. Adding it to the forest will join two trees together.

The forest of trees is a division of the original set of nodes. At first all the trees have exactly one node in them. As the algorithm progresses, we make a union of two of the trees (sub-sets), until the partition has only one sub-set containing all the nodes eventually.

Let us see the sequence of operations to determine the Minimum Cost Spanning Tree(MST) in a graph via Kruskal's algorithm. Suppose the graph of graph shown in figure  and below figure  illustrates the construction of MST of graph of Figure

1339_Kruskals Algorithm.png

Figure: A Graph

Figure: Construction of Minimum Cost Spanning Tree for the Graph by application of Kruskal's algorithm

The following are several steps in the construction of MST for the graph of Figure via Kruskal's algorithm.

Step 1 :  The lowest cost edge is chosen from the graph that is not in MST (initially MST is empty). The cheapest edge is 3 that is added to the MST (illustrated in bold edges)

Step 2: The next cheap edge which is not in MST is added (edge with cost 4).

Step 3 : The next lowest cost edge that is not in MST is added (edge with cost 6).

 Step 4 : The next lowest cost edge that is not in MST is added (edge with cost 7).

Step 5 : The next lowest cost edge that is not in MST is 8 but form a cycle. Hence, it is discarded. The next lowest cost edge 9 is added. Now the MST has all the vertices of the graph. This results in the MST of the original graph.


Related Discussions:- Kruskals algorithm

What is Oscillating Sort?, For the Oscillating sort to be applied, it is ne...

For the Oscillating sort to be applied, it is necessary for the tapes to be readable in both directions and able to be quickly reversed. The oscillating sort is superior to the po

Searching, Searching is the procedure of looking for something: Finding one...

Searching is the procedure of looking for something: Finding one piece of data that has been stored inside a whole group of data. It is frequently the most time-consuming part of m

Program of insertion of an element in list, Program will demonstrate the in...

Program will demonstrate the insertion of an element at desired position /* Inserting an element into contiguous list (Linear Array) at particular position */ /* contiguous_

Mcs-021, #questWrite an algorithm for multiplication of two sparse matrices...

#questWrite an algorithm for multiplication of two sparse matrices using Linked Lists.ion..

Graph terminologies, Graph terminologies : Adjacent vertices: Two vert...

Graph terminologies : Adjacent vertices: Two vertices a & b are said to be adjacent if there is an edge connecting a & b. For instance, in given Figure, vertices 5 & 4 are adj

Omega notation, The ?-Notation (Lower Bound) This notation provides a l...

The ?-Notation (Lower Bound) This notation provides a lower bound for a function to within a constant factor. We write f(n) = ?(g(n)), if there are positive constants n 0 and

Internal sorting, In internal sorting, all of the data to be sorted is obta...

In internal sorting, all of the data to be sorted is obtainable in the high speed main memory of the computer. We will learn the methods of internal sorting which are following:

Queue, algorithm for insertion in a queue using pointers

algorithm for insertion in a queue using pointers

Determine in brief the painter algorithm, Determine in brief the Painter A...

Determine in brief the Painter Algorithm a) The farthest polygon, namely the rectangle PQRS, is stored first. (b) The next farthest, the quadrilateral ABCD, is superpo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd