Ground settlement occurs ahead or behind the jacking face for pipe-jacking?
It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 times of tunnel depth ahead of tunnel face and 80% to 90% of settlement to be finished at a similar distance behind the face. Though in the paper 'Monitoring of ground response associated with pipe jacking works - recent experience in Hong Kong', the author highlighted that based on their experience, development of longitudinal settlement was observed at a distance of 3-4 times of tunnel depth behind the tunnel face and little settlements were reported immediately above the tunnelling face.
HowWet mix macadam is prepare
A rectangular channel is 3 m in width and draws water from a lake. The channel slope is 0.001 and the Manning’s n is 0.0013. What will be the discharge in the channel when the lake
copper and zinc is type of alloy
c programme for Venturimeter
Define the Spalling - underwater inspection of bridge? A spall is a roughly circular or oval depression in the concrete. Corroding reinforcement can cause spalls and reinforcin
Q. Roadworks - filler and binder in bituminous pavement? In bituminous materials, course aggregates perform the bulking action of mixture and contributes to stability of result
Step by step rehabilitation strategies with drawing, figures, and illustrations
• The previous load analysis represents a first and necessary step in the analysis of the given structure but it does not tell us whether the given load can be safely supported (i.
Pipelines: Use of Pipelines in Transport Pipelines are used for transporting liquids (petroleum products for example), gases and solids in slurry form (for example ir
Treatment plant - sewer construction: Problem: How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant? Solution An a
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd