Installation of Meters and Verification of Connections

Apart from testing and calibrating the meters they must be properly installed as per the links diagram. The points in which must be kept in view although meters are installed are given below.

Installation of Meters

a) Position of meter should be such in which reading is simply visible.

b) Mounting of meter should be on solid wall or DP structure or on panel board.

c) Vertical mounting of meters should be ensured. The utility engineer should use a plumb bob and mark a vertical line prior to installation. He could also use a spirit level and put on the top of the meter after hanging on the screw hole. Instead, he should put spirit level on the edge of the terminal block to ensure vertical mounting.

d) For HT metering equipment, CTs should be right on the incoming side before the point of isolation.

e) The meter box should be sealed.

f) The meter recording should be checked at site.


Related Discussions:- Installation of meters and verification of connections

Consequent effects on the real and reactive power losses, Q. Consider an up...

Q. Consider an upgrade of a three-phase transmission system in which the operating line-to-line voltage is doubled, and the phase or line currents are reduced to one-half the previ

Forward and reverse battery bias, Forward and Reverse battery bias In ...

Forward and Reverse battery bias In diagram below(a) the battery is arranged that is why the negative terminal supplies electrons to the N-type material. These types of electr

Find the change in energy received by the charge, Q Acharge of 0.1Cpasses t...

Q Acharge of 0.1Cpasses through an electric source of 6 V from its negative to its positive terminals. Find the change in energy received by the charge. Comment onwhether the charg

How DRAM is different from SRAM, How DRAM's are different from SRAM's?  Why...

How DRAM's are different from SRAM's?  Why DRAMs are said to employ address multiplexing? Dynamic RAM (DRAM) is fundamentally similar as SRAM, except that this retains data for

Working of r digital to analog converter, 2 n -R D/A CONVERTER An n-bit...

2 n -R D/A CONVERTER An n-bit 2 n -R D/A converter needs 2 n resistors of equal value R and (2 n+1 -2) analog switches. A 3-bit 2 n -R D/A converter is shown in Figure, which

Explain the alphanumeric coding - bcd to decimal conversion, Explain the Al...

Explain the Alphanumeric Coding - bcd to decimal conversion? For the inherently binary world of computer, it is necessary to put all symbols, letters, numbers, and so on into bin

Depletion type mosfet, Depletion type MOSFET The channel is of silico...

Depletion type MOSFET The channel is of silicon. It can be two type of channel that is an n-type or p-type channel; it is still mostly silicon. After that, we take note that

Basic architecture of digital switching systems, Q. Explain the basic archi...

Q. Explain the basic architecture of digital switching systems. Explain in detail companding. Ans: A simple N X N time division space switch is displayed in Figure. Switch

Cro, why is delay line used in vertical deflection on systems of CRO?

why is delay line used in vertical deflection on systems of CRO?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd