Installation of band drains, Civil Engineering

Assignment Help:

Question

For drained reclamation, what will significance of smear zone bring by installation of band drains?


Answer

Throughout installation of band drains, smear zones are shaped in that zone of soil surrounding band drains is disturbed. Compressibility of surrounding soils is improved and it results in reduction of their permeability. In fact, surrounding soils are remoulded during installation progression and effectiveness of band drains is summary. In essence, for reduced permeability of soils roughly band drains, it takes longer time to complete consolidation process.

 


Related Discussions:- Installation of band drains

Failure analysis in designing of a structure, Modes of failure • For sa...

Modes of failure • For safe design, a knowledge of the possible modes of failure is also necessary, e.g. failure of the structure could occur due to - Tensile fracture due t

Reverse and direct circulation drill drilling in piling, Q. Reverse and dir...

Q. Reverse and direct circulation drill drilling in piling? For reverse circulation drilling and direct circulation drilling, major difference in drilling method is connected t

surveying, calculation of corrected fore bearings and back bearings i

calculation of corrected fore bearings and back bearings in

Overhanging beams, Do we take the whole length (including the over hanging ...

Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?

Courswork, looking for someone good at structure analysis and design cours...

looking for someone good at structure analysis and design courswork

Weigh batching, measurement of gauge box for sand ?

measurement of gauge box for sand ?

Inadequate pile founding level, Reasons of common occurrence of "inadequate...

Reasons of common occurrence of "inadequate pile founding level" in piles of piers The most severe load on piers usually is the horizontal load owing to berthing and mooring o

Process of lubrication of girder bearing, Q. Process of Lubrication of Gird...

Q. Process of Lubrication of Girder Bearing? Oiling and greasing of bearings is done to ensure that the bearings are well lubricated and working freely to permit expansion and

Spalling reinforcement for pre stressing works, Spalling reinforcement for ...

Spalling reinforcement for pre stressing works in anchor blocks Reinforcement of anchor blocks in prestressing works usuallycomprises equilibrium reinforcement, bursting reinfo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd