Inspection and testing for coating application, Mechanical Engineering

Assignment Help:

Q. Inspection and testing for coating application?

The Applicator shall perform all inspection and testing necessary to assure that the surface preparation and coating application comply with the requirements of this specification. All work shall be subject to the OWNER's inspection. The OWNER shall be the final authority on the acceptability of surface preparation and coating application.

The powder manufacturer's representative shall have access to the Applicator's facilities during the progress of the work to undertake any inspection and testing deemed necessary to ensure that the coatings are properly applied.

The Applicator shall keep the records of operating parameters and inspection and test results, and submit such records to OWNER's inspector on a daily basis, for verification. This daily record keeping and submittal to the OWNER's inspector is important to ensure continuing compliance with the specification.


Related Discussions:- Inspection and testing for coating application

Determine maximum shearing stress in shaft, Determine maximum shearing stre...

Determine maximum shearing stress in shaft:   A propeller shaft 100 mm in the diameter, is 45 m long, transmits 10 MW at 80 rotation per minute. Determine maximum shearing str

Explain the side relief angle, Explain the Side Relief Angle It is angl...

Explain the Side Relief Angle It is angle made by flank of a tool and plane perpendicular to base just under the side cutting edge. if the side relief angle is very large the c

Boiler, Working, specification construction of Lancashire boiler

Working, specification construction of Lancashire boiler

What is tube drawing - cold drawing processes, What is Tube Drawing - cold ...

What is Tube Drawing - cold drawing processes This kind of drawing is very similar to bar drawing process and in majority of cases it is accomplished by the use of a draw be

Mechanical design of the blowdown systems, Q. Mechanical design of the blow...

Q. Mechanical design of the blowdown systems? Mechanical design of the blowdown systems shall be sized for a continuous blowdown of a minimum of 1.0% of MCR. Fabricator may re

If o ring found to be leaking-oil seal is found be leak, If "o" ring is fou...

If "o" ring is found to be leaking or oil seal is found to be leaking check as mentioned: If "O" ring found to be leaking change "O" rings. If oil seal found to be leaking check o

Describe the modes of failure in bearing capacity, Describe the modes of fa...

Describe the modes of failure in bearing capacity. Modes of Failure: Behaviour of foundations subjected to load based on actual observations suggests that the bearing capaci

Working of davis steering gear process, (a) What do you understand by steer...

(a) What do you understand by steering gear ? Explain with a clean sketch the working of Davis steering gear process. Also show the required equation between wheel base and distanc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd