Illustrate an example of a critical path given by activity, Project Management

Assignment Help:

Illustrate an example of demonstrating a network or critical path by given activity and duration.

Activity                      Duration (Wks)                   Preceded by

A                                 5                                   -

B                                 4                                   -

C                                 3                                   B

327_Demonstrating a network or critical path.png

a. The elapsed or expected completion time of the project is eight weeks

b. The critical path activities are as A and C for example both should be completed into their predicted durations, or else the project will be longer into duration than eight weeks. See how the EET and LET of critical activities are the same.

c. Activity B is a non-critical activity and that would have a float time of one week.

d. This is since its predicted duration is four weeks, but this can take five weeks to finish and yet leave enough time left for activity C to be finished, the elapsed time of the project will still be attained. See how the EET and LET both of non-critical activities are not same; the difference is one week for example the float time, while you deduct one by the other.

e. The broken arrow or dummy activity preserves logic into the diagram for example visually you can observe that both activities A and B should be finished, before C can begin. See also that the arrow showing activity C starts by circle 3 (not circle 2), this is since the earliest event time for C would be 5 weeks not 4 weeks like circle 2 exhibits.


Related Discussions:- Illustrate an example of a critical path given by activity

Explain the role of the project owner and project sponsor, X Company, a pri...

X Company, a private security firm, has signed a contract to fund the design, construction and running of a local police station. This arrangement is a public private partnership a

What is culture of organisation where study and work done, Consider the org...

Consider the organisation which employs you or where you study. What is the culture of this organisation? Why does this have that exacting culture? What organisational culture woul

Process control, All processes are subject to various influences such as ...

All processes are subject to various influences such as mechanical electrical and environmental changes which is tend to deviate the process from its initial setting. The

The three flows in Supply Chain Management, Hi can you please provide info ...

Hi can you please provide info on referencing material and more detailed info on the three flows in supply chain management?

What is the primary objective of controlling, What is the primary objective...

What is the primary objective of controlling? The main objective of controlling is to bring the actual operational performance of enterprise onto the accurate track according t

Line balancing methods, Line Balancing Methods  The various line balan...

Line Balancing Methods  The various line balancing methods or techniques used are: Heuristic Methods Linear Programming Kilbride and waste Methods

Processes by market orientation , Processes by Market Orientation Pro...

Processes by Market Orientation Processes can  also be categorized on the basis  of four  marker orientations: Make to Stock (MTS): the goods usually are standard mat

Determine elapsed time of critical path, Determine elapsed time of critical...

Determine elapsed time of critical path when The critical path is given by points BCFG and the elapsed time 17 weeks. There D can over running by up to 3 weeks without

What are the benefits of doing a job safety analysis, Question: A sewer...

Question: A sewer line is to be connected to a school. This work will be carried out in a 2.4 meters deep excavation and will be routed through the playground, which was once

Why is necessary to plan an is project in detail before work, Give three re...

Give three reasons why this is necessary to plan an IS project in detail before starting work on this. Only the simplest projects that probably imply one developer working for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd