How much hours of production time would you schedule for x, Operation Management

Assignment Help:

Plans are being made to produce a product that requires 40 minutes on Resource X and 30 minutes on resource Y. Assume that there is only one of each of these resources, and that market demand is 1400 units per month.

How many hours of production time would you schedule for X and Y? What would happen if both were scheduled for the same number of hours?


Related Discussions:- How much hours of production time would you schedule for x

Explain evidence you have seen if the imperatives for change, Discuss evide...

Discuss evidence you have seen if the imperatives for change, flexibility, and responsiveness faced by today's firms.

Disadvantages, What are the disadvantages of operation management?

What are the disadvantages of operation management?

Find which city provides the lowest overall costs, Kelly Trucking, Inc., is...

Kelly Trucking, Inc., is planning a new warehouse to serve the western United States. Denver, Santa Fe, and Salt Lake City are under consideration. For each location, annual fixed

How is value of product effective on operational strategy, How is the value...

How is the value of product effective on operational strategy? Value is the cause why customers choose one rivals product over other, when an organisation can give certain uniq

Explain how many hours would the average laborer, In December, general moto...

In December, general motors produced 7,200 customized vans at its plant in Detroit. The labor productivity at this plant is known to have been 0.10 vans per labor hour during that

Describe why financial objectives essential for the company, Why do financi...

Why do financial objectives essential for the company to succeed?

Describe what role organizational structure plays, Discuss what role organi...

Discuss what role organizational structure plays in an organization's efficiency & effectiveness

Explain how many mocha latte coffees would be forecast, 4.31 Coffee Palace'...

4.31 Coffee Palace's manager, Joe Felan, suspects that demand for mocha latte coffees depends on the price being charged. Based on historical observations, Joe has gathered the fol

Define the minimum and maximum cycle times, An assembly line with 11 tasks ...

An assembly line with 11 tasks is to be balanced. The longest task is 2.7 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 18 minutes. The line will oper

Explain what is the wacc, Midwest Electric Company (MEC) uses only debt and...

Midwest Electric Company (MEC) uses only debt and common equity. It can borrow unlimited amounts at an interest rate of rd = 10% as long as it finances at its target capital struct

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd