Histograms

Histograms show a visual summary of the data, which is simple to understand. Raw data is difficult to understand and a pictorial representation helps to understand it better. In such cases this tool can be used. It is a type of bar graph that deals with data that exists in a continuous range from a lower number to a higher number. It displays the frequency of occurrence of an individual data points across the data from low to high. Histogram can be more easily understood than a table of collected numbers. The six steps for creating and using histograms are:

1.  Select  the  measure  to  be  examined: Typical measures are sizes, speed, time, weight, dimensions, and so on

2.  Collect the data: A check sheet may be useful. Data may already exist in some tabular form or spread sheet.

3.  Prepare a frequency table: It is a summary of data in a sequential format. This is the first step of organising data.

4.  Design the histogram: These are constructed in a disciplined way.

5.  Draw the histogram: Enter the data and prepare the graphic display. Chart making capabilities are available in most of the word-processing and spreadsheet programs, these will help in this step.

6.  Interpret the data: View the bars of the histogram and analyse their relationship to each other.


Related Discussions:- Histograms

Element of total quality management, In order to adopt and initiate TQM ...

In order to adopt and initiate TQM within any organization it is necessary to understand the key elements. These elements which form the essential core of the TQM phil

Product development cycle, The product development cycle starts with th...

The product development cycle starts with the assessment of the customers needs and ends when the design is finally released for bulk production. The main steps in th

Continuous improvement - elements of tqm, Continuous improvement: The ...

Continuous improvement: The library should set goals for continuous improvement. To develop this a focus  on training,  education, communication, recognition  of achievements

Determine acceptance criteria for a project derived, From what product must...

From what product must the acceptance criteria for a project is derived and why? The acceptance criteria must be derived by the Requirements Specification that is where the use

Different stages in the negotiation process, In the face of rising costs, t...

In the face of rising costs, the senior management in PT Company has decided that significant cuts will be needed in the budgets of some of its departments. The promotional budget

Identify the critical path by activities and duration, Identify the critica...

Identify the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

Risk breakdown structure (rbs) , Risk Breakdown Structure (RBS)  R isk...

Risk Breakdown Structure (RBS)  R isk Breakdown Structure (RBS) is a tool developed by Dr. David Hillson that is used to guide the risk management process. He describes RBS as

Super Bowl, Do you have an assignment which has WBBS and project plan for p...

Do you have an assignment which has WBBS and project plan for planning of Super Bowl Half time planning?

Principal problems of managing projects in organisation, What are the princ...

What are the principal problems of managing projects in a fully functional organisation structure? The major problems of functional organisations are to perform with what may b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd