Grouted or Penetration Macadam:
This is a specification where the binder is sprayed on a compacted layer of stone aggregates and is allowed to penetrate and bind the aggregates. A layer of intermediate aggregates, called key aggregates, is spread on the layer and rolled. A seal coat is provided to seal the surface.
For a 50 mm compacted thickness, the quantity of coarse aggregates is 0.60 cu m per 10 sq m area, the quantity of binder is 50 kg per 10 sq m, and the quantity of key aggregates is 0.15 cu m per 10 sq m. The seal coat is similar to the seal coat provided for a PC.
The advantage of penetration macadam is that it does not require a mixing plant. The advantage is that it uses a high quantity of binder. The specification is hardly used now-a-days.
in direct pumping system
Equalization Basins - Hydraulic System For influent flow to publicly owned treatment works (POTWs), flow rates may be excessive for short or long durations, especially in combi
Define Dual frequency and colour fathometer - Sounding/Sensing Devices? Dual Frequency and Colour Fathometers can be used to detect refill in the scoured area since more than o
Classification of Timber Several bases are considered for the classification of timbers. The following are the essential basis: Mode of growth Modulus of elasticity
Explain the Signalized Intersections Cycle length - the time required for one complete sequence of all signal indications Phase - the right-of-way (green), change (yellow),
Design of the Aeration Basin Based on Solids Retention Time - sewer construction: You are provided the following information about a municipal wastewater treatment plant. That
Explain a Critical Path The series of activities which determines the earliest possible date of project completion Usually defined as those activities with minimal or
types of staircases.
Q. Function of prime coat in bituminous pavement? The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the pre
What is the Loss of Prestress due to Shrinkage of Concrete It is the loss of prestress due to shrinkage of concrete, which takes place in the initial stage of hardening of conc
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd