Grouted or penetration macadam, Civil Engineering

Assignment Help:

Grouted or Penetration Macadam:

This is a specification where the binder is sprayed on a compacted layer of stone aggregates and is allowed to penetrate and bind the aggregates. A layer of intermediate aggregates, called key aggregates, is spread on the layer and rolled. A seal coat is provided to seal the surface.

For a 50 mm compacted thickness, the quantity of coarse aggregates is 0.60 cu m per 10 sq m area, the quantity of binder is 50 kg per 10 sq m, and the quantity of key aggregates is 0.15 cu m per 10 sq m. The seal coat is similar to the seal coat provided for a PC.

The advantage of penetration macadam is that it does not require a mixing plant. The advantage is that it uses a high quantity of binder. The specification is hardly used now-a-days.


Related Discussions:- Grouted or penetration macadam

Determine the coordinate for point r, For the project work points (x,y) sho...

For the project work points (x,y) shown in the figure the bearing of point R is due West. The coordinate for point R is most nearly:    Solution: Determine the length o

State the term - calculation of deformation of concrete, State the term - c...

State the term - calculation of deformation of concrete For the calculation of deformation of concrete at some stage before the maximum shrinkage is reached, it may be assumed

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Explain about viscous flow loss, Q. Explain about Viscous flow loss? Ab...

Q. Explain about Viscous flow loss? Absorptive material comprises interconnected voids and pores into which sound energy will propagate. When sound waves pass throughthe materi

#titl, Two readings ie 1.64m and 0.73m were taken during leveling procedure...

Two readings ie 1.64m and 0.73m were taken during leveling procedure to define the slope of a centerline of a bridge at points A and B. If distance AB=50 m, find the slope of line

Compaction, describe how quality control is maintained in a rolled fill dam...

describe how quality control is maintained in a rolled fill dam

Major compensation of using hdpe as compared with cast iron, Question N...

Question Now, mainly flap valves are ended of HDPE. What is the major compensation of using HDPE as compared with cast iron? Answer (i) It has no response with sewage a

Frames, how to analyse a frame

how to analyse a frame

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd