Grouted or Penetration Macadam:
This is a specification where the binder is sprayed on a compacted layer of stone aggregates and is allowed to penetrate and bind the aggregates. A layer of intermediate aggregates, called key aggregates, is spread on the layer and rolled. A seal coat is provided to seal the surface.
For a 50 mm compacted thickness, the quantity of coarse aggregates is 0.60 cu m per 10 sq m area, the quantity of binder is 50 kg per 10 sq m, and the quantity of key aggregates is 0.15 cu m per 10 sq m. The seal coat is similar to the seal coat provided for a PC.
The advantage of penetration macadam is that it does not require a mixing plant. The advantage is that it uses a high quantity of binder. The specification is hardly used now-a-days.
Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang
A retaining wall 3.6 m high supports a dry cohesion less backfill with a plane ground surface sloping upwards at a surcharge angle of 20° from the top of the wall. The back of the
Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greater tha
Based on the information provided in Figure, the difference in elevation between BM and TP 2 is most nearly: Solution: Set up a Table as shown below and insert the kno
Construction of Embankment: The following steps describe embankment construction : (a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed
Question Given a 1meter high staircase resting on solid concrete, could it be adequate to design nominal reinforcement for staircase? Answer For design of staircase,
advantage of concrete floor
factor affecting scheduling
Q. What do you understand by Percolation of water? Percolation of water into the ground or embankment takes place, causing rise in water table and / or saturation of the body.
Compass surveying
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd