Forecasting system outputs, Mechanical Engineering

Assignment Help:

Forecasting System Outputs:

In a company, inventory level is reviewed biweekly. If the parts used in an assembly have the lead time of one and a half week, what period should a forecast of requirements of parts cover for replenishment?

Solution

Forecast period = lead time + review period

= 1.5 weeks + 2 weeks

= 3.5 weeks

However, the replenishment of parts needs a forecast of requirements at least 3.5 weeks into the future.


Related Discussions:- Forecasting system outputs

Gear torque output, what is the different torque rating of a helical gear o...

what is the different torque rating of a helical gear one direction verses the other

Explain the procedure of removal for valves, (a) Explain the procedure of r...

(a) Explain the procedure of removal for valves. (b) How should one remove valve guide from cylinder head? (c) What is the use of piston side base? (d) What is the use of

Thermal reservoir - thermodynamics, Thermal Reservoir - Thermodynamics: ...

Thermal Reservoir - Thermodynamics: Thermal Reservoir. A thermal reservoir is the part of environment that can exchange heat energy with system. It has adequately large capa

Brakes drag motorcycle problem, If Brakes Drag Causes of P...

If Brakes Drag Causes of Problem Remedy   Insufficient pedal free play Recommended brake fluid not used

Cement, wet process of portland cement

wet process of portland cement

Pressure - thermodynamics, Pressure - Thermodynamics: While working in...

Pressure - Thermodynamics: While working in the system, thermodynamic medium exerts a force on boundaries of vessel in which it is kept. The vessel may be a container, or an e

Explain the manufacturing process, MANUFACTURING PROCESS A manufacturin...

MANUFACTURING PROCESS A manufacturing process is the activity (or a combination of activities) of transforming a given material into a product of different forms and sizes and

Find out the proof load in close coiled helical spring, Find out the proof ...

Find out the proof load in close coiled helical spring: A close coiled helical spring is built of 6 mm diameter wire. The coil diameter is equal to 80 mm, number of coil is 10

Show hazard assessment of plant operation, Q. Show Hazard assessment of pla...

Q. Show Hazard assessment of plant operation? Using the hazard assessment of each plant operation will help establish the layout or orientation of process units within the plan

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd