Float or slack of an activity is positive or negetive, Civil Engineering

Assignment Help:

1. What take place when float or slack of an activity is positive

Ans: It represents a situation where extra resources are available and the completion of the project is not delayed

2. What take place when float or slack of an activity is negative

It represents that a project falls behind schedule and additional resources are required to complete the project on time

 

 


Related Discussions:- Float or slack of an activity is positive or negetive

BRIDGES, WHAT ARE THE DIFFERENT TYPES OF BRIDGES

WHAT ARE THE DIFFERENT TYPES OF BRIDGES

DC POWER SUPPLY, DESIGN A LINEAR DC POWER SUPPLY WITH THE FOLLOWING SPECIFI...

DESIGN A LINEAR DC POWER SUPPLY WITH THE FOLLOWING SPECIFICATION,SHOW DETAILS STEPS AND CALCULATION...Vload :12v Iload :0.07A Vripple load(p-p) :0.01v TA :45 DEGREE CELCUS

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Survey chain, describe gunters chain in survey

describe gunters chain in survey

Remedial measures for problems in turbid water - reflection, Remedial measu...

Remedial measures for Problems in Turbid Water - Reflection? The problem of reflection can be minimised by carefully placing the flash away from the axis of the camera and at a

SETTLEMENT OF SOIL AND BRACING OF RETAINING WALL OF BASEMENT, STRUCTYRE IS ...

STRUCTYRE IS HAVING BASEMENT JUST WITH THE SIDE OF FOUNDATION WHICH CAUSED SETTLEMENT AND CRACKS IN THE STRUCTURES

Void ratio and dry density of a soil, Q. Define water content, void ratio ...

Q. Define water content, void ratio and dry density of a soil. If wet density of a soil is 1.9 gm per cm at a moisture content of 24%, what will be its dry density?  Ans. - W

Widening on curves, Widening on Curves: Pavements have to be widened ...

Widening on Curves: Pavements have to be widened on curves because of the fact that : (a) the vehicle has a wheel base and overhang on the front and rear, and the vehicle

Optimum binder content in bituminous pavement, Q. Optimum binder content in...

Q. Optimum binder content in bituminous pavement? Amount of binder to be added to a bituminous mixture can't be too excessive or too little. Principle of designing the optimum

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd