Float or slack of an activity is positive or negetive, Civil Engineering

Assignment Help:

1. What take place when float or slack of an activity is positive

Ans: It represents a situation where extra resources are available and the completion of the project is not delayed

2. What take place when float or slack of an activity is negative

It represents that a project falls behind schedule and additional resources are required to complete the project on time

 

 


Related Discussions:- Float or slack of an activity is positive or negetive

What is the design mix concrete, What is the Design Mix concrete Determ...

What is the Design Mix concrete Determination of  the proportions of  cement, aggregates and water to  achieve the required strengths in concrete is made by designing  the  con

Sand cone test – suitable for all soils?, Q. Sand cone test – suitable for ...

Q. Sand cone test – suitable for all soils? Sand cone (replacement) test is generally carried out to determine the in-situ and compacted density of soils. This testing method i

Paints., contituents of paints

contituents of paints

Show the stresses during pile driving, Q. Show the Stresses during pile dri...

Q. Show the Stresses during pile driving? Stresses during pile driving In pile driving operation, proper selection of piling hammers is necessary to prevent the damage of

Survey, what is road survey ?

what is road survey ?

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

Describe the terms inside clearance and outside clearance, a) Explain with ...

a) Explain with a neat sketch how will you carry out the wash boring method of soil exploration. What are its merits and demerits? b) Describe the terms 'inside clearance' and '

Correction for construction period, You are aware that construction of any ...

You are aware that construction of any type of structure takes sometime. Pressure due to the building will be applied gradually and not instantaneously. Excavation for the construc

Turbines, application of turbines 2 the civil engineering aspect

application of turbines 2 the civil engineering aspect

Shape factor, For a solid circular shaft transmitting torque, the shape fac...

For a solid circular shaft transmitting torque, the shape factor is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd