Q. Athree-phase, 60-Hz substation bus supplies two wye-connected loads that are connected in parallel through a three-phase feeder that has a per phase impedance of 0.5 + j2 . Load 1 draws 50 kW at 0.866 lagging PF, and load 2 draws 36 kVA at 0.9 leading PF. If the line-to-line voltage at the load terminals is 460 V, find the following:
(a) Total line current flowing through the feeder.
(b) Per-phase impedance of each load.
(c) Line-to-line voltage at the substation bus.
(d) Total real and reactive power delivered by the bus.
Q. A three-phase load, connected to a 440-V bus, draws 120 kWat a power factor of 0.85 lagging. In parallel with this load is a three-phase capacitor bank that is rated 50 kVAR . D
Explain the significance of the loss tangent of a dielectric material. The loss tangent contains a very small value for free space. For solid materials there tan δ = 0.003, tha
Example of binary subtraction - positive number Case 1. Positive number is more than negative number ( i e, answer is positive) Example subtract 4510 ( 1011012
WRITE THE PROCEDURE CONDUCT OC AND SC TEST OF AN ALTERNATOR TO FIND SYNCHRONOUS IMPEDENCE
Q. Why we need digital systems? EASIER TO PROCESS: For the reason that digitized information breaks all information into discrete units the information is easier to process and
how can I simulate air variable capacitors in cst simulator?
Loudspeakers using single driver are unable to cover the entire frequency band from low frequency to high frequency. Sometimes multiband frequency is required for the bass enhancem
i have an assignment due for submission within two days. It is all about transformer measurement manually and numerical results using Matlab.Is there anyone can do the job?
how do we construct wind turbines. procedures methods
Installation of Meters and Verification of Connections Apart from testing and calibrating the meters they must be properly installed as per the links diagram. The points in wh
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd