Feedback - advantages of statistical process control, Operation Management

Assignment Help:

Feedback - Advantages of Statistical Process Control 

SPC is a clear example of negative-feedback system control, providing management with timely information on the state of the process, allowing corrective action to be taken if required. Equally, SPC indicates when a process should be left to run, thereby saving on unnecessary adjustments to the process and, perhaps, avoiding non- conformance which could result from such adjustments. The following simple example may help to make the latter point clear. Consider a process with a target output value of 10.0 which, when running in a stable manner, has an inherent variability (see common cause variability, later) such that 50 per cent of the output is at the mean output value, 25 per cent measures 0.1 below, and the balance of 25 per cent measures 0.1 above the mean output value. Assume that the initial process setting is such that the mean output value matches the target value of 10.0. Twelve consecutive measurements might produce the following results (see table). Note that none of the measured values are outwith the expected range: with SPC, no adjustment of the process would be recommended.

53_Feedback - Advantages of Statistical Process Control.png

Now consider the same situation in the absence of SPC. The operator can adjust the process setting but cannot directly determine its mean value: he can only measure individual instances of the output, which, as we have seen, may differ from the mean as a result of the inherent variability of the process. Suppose, now, that the operator measures each output, calculates the deviation from the target value and adjusts the output by that amount. In the next table, the first output value (10.1) is above the target value (10.0) by 0.1. He adjusts the process setting to reduce the output value by this amount but, unknown to him, the process setting is now 9.9. As a result, the second output value is 9.8, not 9.9 (as it was in the previous table). The deviation is now 0.2 below target. The operator adjusts the process to increase the output by 0.2, taking the mean setting from 9.9 to 10.1, and so on.

1528_Feedback - Advantages of Statistical Process Control 1.png

Notice the effect: under SPC, as shown in the first table, six of the values would be at the target value and the others would range between 0.1 above to 0.1 below target. In the absence of SPC, as shown in the second table, only two of the values are on target and the others range from 0.1 above to 0.2 below target. The process adjustments have increased the variability of the output.


Related Discussions:- Feedback - advantages of statistical process control

Explain what is the value of the game, Consider the following two-person ze...

Consider the following two-person zero-sum game. Assume the two players have the same two strategy options. The payoff table shows the gains for Player A.               Player B

Explain self-preservation is not the highest value, Are there situations in...

Are there situations in which self-preservation is not the highest value?

Depict an aon diagram of the project, The following is a table of activitie...

The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede- Activity Duration (weeks) Prece

ERP, DETAIL THE WORKFLOW OF HRM THAT DEPLOYES ERP

DETAIL THE WORKFLOW OF HRM THAT DEPLOYES ERP

Labour intensity - operations function, Labour Intensity - Operations Funct...

Labour Intensity - Operations Function Labour intensity is defined as the ratio of the labour cost incurred to the value of the plant and equipment employed. It is important t

Explain skills associated with effective project manage, Determine which of...

Determine which of the eight traits or skills associated with being an effective project manager would be the most effective when managing a group of newly hired engineers. Justify

Compute the expcted inflation rates for each year, The Fed is concerned wit...

The Fed is concerned with interest rate levels and the possibilitiy of inflation. Given the gollowing information, calculate the expected inflation premiums over hte next three yea

Explain what is resource levelling, Answer the following questions: 1) ...

Answer the following questions: 1) What is resource over allocation? 2) What is resource levelling? 3) Under what circumstances would you want to manually reso

Determine the overall project completion time, Question : (a) Under wha...

Question : (a) Under what conditions is PERT preferred to CPM in project management ? Illustrate your answer with examples of projects. (b) Several stages are involved in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd