Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Roles of b as the project sponsor and r, DG Company has made a significant ...

DG Company has made a significant investment in a project to develop a new client management IT system, which when implemented should help give the company a competitive edge.  How

What is the use of critical path analysis as a tool, What is the use of cri...

What is the use of critical path analysis as a tool? The use of critical path analysis as a tool: a. It is good visual communication and planning tool for effectual time man

The Walsham Hotel, Compare and Contrast the KN346 investment and the "plain...

Compare and Contrast the KN346 investment and the "plain vanilla" alternative.

Backward integration, Backward Integration A strategy in which an orga...

Backward Integration A strategy in which an organization builds competitive benefits by controlling the provider of the raw materials needed to make its products.

Management of utilities for a estate complex, Question 1: (i) What are...

Question 1: (i) What are the various aspects you would consider while planning to build a new international airport? (ii) With relevant arguments discuss the necessity or

Tolerance and surface finish, Tolerance and Surface Finish Design engi...

Tolerance and Surface Finish Design engineers are always blamed of specifying closer tolerances than necessary. It  is obvious that to achieve a tolerance of ± 0.001 mm is mor

PERT Network Analysis, Solve the following CPM/PERT Network Analysis proble...

Solve the following CPM/PERT Network Analysis problem: Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slac

Explain about the term project initiation document, Explain about the term ...

Explain about the term project initiation document. A project initiation document (PID) that is project proposal document or charter, is a report to illustrate a business case

Advantages of rules-planning function, Advantages of Rules In addition ...

Advantages of Rules In addition to the general societal advantage of rules referred to above, the organization and its employees can derive the following benefits from the inst

Discuss the objectives of performance appraisal, Question 1: a) What ...

Question 1: a) What is performance appraisal and discuss the objectives of performance appraisal? b) Elaborate on the different techniques of performance appraisal an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd