Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Steps of project manager to enhance likelihood of project, Ideally, the nee...

Ideally, the need for an IS project would be given in some detail before planning begins. When the requirement is not detailed adequate, what steps can the project manager take to

Human resource management in the public sector, Problem : "In the face ...

Problem : "In the face of daunting challenges, governments are compelled to develop a new style public sector with systems that foster innovation and the creative energy of sta

Describe reck and long''s purchasing development model, Describe Reck and L...

Describe Reck and Long's purchasing development model. Supply is now accepted as a more fundamental and strategic method when compared to purchasing. Twenty years ago Reck and

Basic control elements in generic projects, QUESTION Implementation sh...

QUESTION Implementation should focus on the achievement of agreed outcomes, so that if a problem is encountered with the plan, other courses of action will be employed. Wha

Disaster recovery preparation - training, Question 1: Unplanned catastr...

Question 1: Unplanned catastrophes are always waiting just around the corner to derail your project. You have been appointed risk manager to prepare a risk management plan, and

Shareholder value - measure for project management value, S hareholder val...

S hareholder value Project management initiative brings a renewed interest among the shareholders. The major investors show more interest by becoming active in the organisati

Aggregate planning, Aggregate planning is an operational method that does ...

Aggregate planning is an operational method that does an aggregate plan for the production procedure, in advance of 2 to 18 months, to provide an idea to management as to what amo

The purpose of a project initiation document, S Company has been awarded th...

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this s

What are the advantage of bottom-up decentralised approaches, What are the ...

What are the advantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager or

Continuous improvement - total quality management, Do it Right First Tim...

Do it Right First Time : TQM adopt the policy of zero defect. There is no scope for rework and rejection. The right first time or zero defect is the result of an empha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd