Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Describe what is a budget process, Question: (a) John Oakland says: ...

Question: (a) John Oakland says: "Day to day issues, often taken for granted, involve quality in some form or other. For example, the safety and conformity with accepted st

Production planning, PRODUCTION PLANNING AND SCHEDULING OF A GARMENTS MANUF...

PRODUCTION PLANNING AND SCHEDULING OF A GARMENTS MANUFACTURING COMPANY 1. Introduction TREND SHOPS SDN BHD is a manufacturing unit of (mid-upmarket) ladies garments.  It

Design and implementation of the pms, Question: Performance appraisal (...

Question: Performance appraisal (PA) and management play an important role in the effective management of employees in every viable organisation. However, for many Human Resour

What is the use of gantt charts as a tool, What is the use of Gantt Charts ...

What is the use of Gantt Charts as a tool? The use of Gantt Charts as a tool: This tool can be used to plan time scale for a project This tool can be used to approxima

What is project scheduling, Question 1 Briefly explain various activities ...

Question 1 Briefly explain various activities involved in project management Question 2 What is COCOMO? Write necessary steps for cost estimation Question 3 What is proj

Aim and objective of syringe management plan, Aim The purpose of the Sy...

Aim The purpose of the Syringe management plan is to protect the social community against injury by syringe and help people manage syringe in proper manner. According to the re

Calculate how much float/slack time, ST is the operations director of F Bak...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

Application development for the multinational, Question: (a) What coul...

Question: (a) What could be the motivations for a large multinational to offshore its application development? (b) What could be the risks of offshoring application develo

Quality tools in process improvement, Question : (a) Describe the impor...

Question : (a) Describe the importance of the following quality tools in process improvement: (i) Pareto diagrams (ii) cause-and-effect diagrams (b) The Managi

Advantages and disadvantages of having a matrix structure, Explain the adva...

Explain the advantages AND disadvantages of having a matrix structure for managing a project. For projects that require a range of skills and involvement of staff from dissimil

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd