Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Problems associated with policies-planning function, Problems associated wi...

Problems associated with policies 1) Policies are liable to different interpretations since they allow discretion and are usually broad. If made specific they become rules and th

Draw a control chart for the number of defects, Explain the concepts involv...

Explain the concepts involved in Product Layout and its advantages and disadvantages vis-a-vis process layout. 18 carpets were observed closely and the number of defects in thei

Project cost management, Your project sponsor has asked you and your team t...

Your project sponsor has asked you and your team to refine the existing cost estimate for the project so that there is a solid cost baseline for evaluating project performance. Rec

Parameters of facilities planning and design, Question 1: Distinguish b...

Question 1: Distinguish between innovation and renovation within the parameters of facilities planning and design. Question 2: Although security and safety at the work

#title.Discountingw., what is the principle of discounting and what issues ...

what is the principle of discounting and what issues are critical in this process

What do you mean by line balancing in management, What do you mean by Line ...

What do you mean by Line Balancing in management? Line Balancing: It means balancing the line among the product lines or assembly lines. This aims at grouping assists an

What is quality system , Quality System  The basis of our Quality System...

Quality System  The basis of our Quality System is the industry standards/ best practices and the guidance of the ISO 9001:2008 requirements. This ensures that both quality and

Transaction cost theory could help the head of insurance, The Head of Insur...

The Head of Insurance at JKL Bank has been considering how to make efficiencies in the operation of the Car Insurance Business Unit. One option under consideration is to outsource

WBS and Network diagram, Network Diagram for my course project based upon t...

Network Diagram for my course project based upon the WBS. The Network Diagram should include the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF), a

The purpose of a project initiation document, S Company has been awarded th...

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd