Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Risk management, how do I create a risk management plan

how do I create a risk management plan

Risk categorisation , Risk Categorisation  Management of risk involves:...

Risk Categorisation  Management of risk involves:    Prevention: To deal with causes.    Recovery: To deal with effects.  There are three categories of project r

Types of histograms, H i stograms are of five types. They are: B...

H i stograms are of five types. They are: B ell shaped: It can be applied for concepts such as average and standard deviation. D ouble peaked: It is used to com

Result of management project to prevent false expectations, What would be t...

What would be the result of management project to prevent the development of false expectations? Into the initiation phase, the project management partners enter a temporary co

Policies-planning function, Policies are general statements to guide...

Policies are general statements to guide subordinate thinking in the decision making process. policies define the area within which a subordinate may make a decision. In

Tools and techniques of layout planning - templates, Tools and Techniques o...

Tools and Techniques of Layout Planning - Templates Templates are most commonly employed when preparing layouts. Templates are two dimensional (2D) or block templates consist

Project management requires three important activities, Question (a) Pr...

Question (a) Project Management requires three important activities, namely planning, estimation and scheduling. Discuss the differences between them. (b) Scheduling of proj

Usage of risk breakdown structure , Usage of RBS  Once an organisation ...

Usage of RBS  Once an organisation defines a Risk Breakdown Structure (RBS), then it can be used in a number of ways. These RBS is relevant across the project and helps in the

Preliminary design, Having given the guidelines in the form of design s...

Having given the guidelines in the form of design specifications the designer should be given a free hand in developing the preliminary design of the product. However i

Project risk profile owners, Project risk profile owners  Project risk ...

Project risk profile owners  Project risk profile owners must make sure that they deal with each and every risk of the project. The responsibilities of the project risk owners

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd