Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Decide modules, There are also seven decide modules on our model. The first...

There are also seven decide modules on our model. The first one decides whether patients need a wheel chair or not; if yes, they will be sent to a clerk who is responsible for spec

Describe edgar scheins levels of organisational culture, Problem 1: Des...

Problem 1: Describe the importance of Employee Relations Management in an organisation. Describe employee relations management Importance of employee relations managem

State the principle of extrapolating, The analysis effort and programming m...

The analysis effort and programming methods both rest onto the principle of extrapolating the total development effort by detailed evaluates of one phase of the project. Define the

Determine the analogy method of estimating, The analogy method of estimatin...

The analogy method of estimating is frequently used to produce broad-brush evaluates at the start of a project. Why this method is mainly suited to such application? Determinin

Work breakdown structure, Work breakdown structure: The work breakdown ...

Work breakdown structure: The work breakdown structure, as its name suggests, represents an organised and logical break down of the project into its component parts. Thus break

Third elaboration iteration, Perform a status assessment of the third Elabo...

Perform a status assessment of the third Elaboration iteration. DO NOT GENERALISE. Assess each activity separately and assess it against the outcomes specified for the activity. Ge

Draw a gantt chart and network diagram, Use the WBS you developed in Questi...

Use the WBS you developed in Question to create a project plan with a Gantt chart in Microsoft Project for the project. Clearly identify the milestones for this project. Estimate t

Cause-orientated organisations, Non-political, not-for-profit, cause-orient...

Non-political, not-for-profit, cause-orientated organisations drawn from more than one country are known as  Non-governmental organisations (NGOs).

Marketing project, Step 1 Advise the instructor in writing if you will be w...

Step 1 Advise the instructor in writing if you will be working on the project individually or with another class member(s). Choose your team member (s),carefully, as you will have

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd