Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

PERT Network Analysis, Solve the following CPM/PERT Network Analysis proble...

Solve the following CPM/PERT Network Analysis problem: Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slac

System layout planning activity relationship chart , System Layout Planning...

System Layout Planning Activity Relationship Chart Systematic layout planning (SLP) method is used in some production systems such as service systems, where the amount of mate

Mapping project - mapping system, i. Select a small mapping project appl...

i. Select a small mapping project applicable to your 'mapping' system that aims to present a theme or specific solution (e.g. tourist map, farm map, habitat map, etc.). ii.

How to, i get stuck being on time and orginzed. please help. is this money?...

i get stuck being on time and orginzed. please help. is this money? thanks isabella

What are the advantages of division of labour, What are the Advantages of D...

What are the Advantages of Division of Labour? Advantages of Division of Labour: As very similar worker does the same work frequently:- a. It gains proficiency and ski

Discuss the project management knowledge areas, Question: (a) Project ...

Question: (a) Project Integration Management refers to the integration of the nine knowledge areas and project phases involved in coordinating project activities to ensure th

Explain de-centralized management model, Solution-if I am the owner of the...

Solution-if I am the owner of the three coffee shops within a 50 mile radius, then I would adopt a de-centralized management model having self directed teams. This will help me in

Organization of material management, Organization of Material Management: ...

Organization of Material Management: To  facilitate  planning direction  control and co ordination of  various activities  related to material in an  enterprise  thee should

Process of packaging and labeling of the product, Q. Process of Packaging a...

Q. Process of Packaging and labeling of the product? Packaging of biscuits involves both the primary and secondary packets. These primary package should be laminated paper whi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd