Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Discuss the project management knowledge areas, Question: (a) Project ...

Question: (a) Project Integration Management refers to the integration of the nine knowledge areas and project phases involved in coordinating project activities to ensure th

Housekeeping, what is the thumb rule to calculate the housekeeping manpower...

what is the thumb rule to calculate the housekeeping manpower requirement in office

Too much too soon, What is operational and behavioural symptoms

What is operational and behavioural symptoms

Objectives of a procurement system, Question 1: (a) Enumerate five obje...

Question 1: (a) Enumerate five objectives of public procurement systems contained in the UNCITRAL Model Law on Procurement of Goods and Construction. (b) Compare and c

Project communication management processes, Question: (a) The greatest ...

Question: (a) The greatest threats to many projects are failures to communicate effectively. (i) Elaborate on the Project Communication Management processes (ii) Briefly

Advantages of quality control system, Reduction in Costs : An efficient qua...

Reduction in Costs : An efficient quality control system reduces the cost of production of the product due to reduction in wastage of raw materials, semi finished and finished good

Evaluation of the prototype, At this stage of design the designer will...

At this stage of design the designer will invariably by under tremendous pressure to quickly finish the design and pass it on for production. This is so because even w

What is working of definition phase in project management, What is the work...

What is the working of definition phase in the project management? Definition phase: After the project plan that developed into the initiation phase, has been approved, a

Operating characteristic curve, O perating characteristic curve The op...

O perating characteristic curve The operating characteristic curve for a sampling plan quantifies the risks. The OC curve for an attribute plan is a graph of the percentage de

What are its core features of mpmm, MPMM is a body of project management co...

MPMM is a body of project management content, wrapped in an easy, simple to use software tool. This tool contains such core features as a Navigation Panel, Display Panel, Page Summ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd