Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Work breakdown structure, Work breakdown structure: The work breakdown ...

Work breakdown structure: The work breakdown structure, as its name suggests, represents an organised and logical break down of the project into its component parts. Thus break

What are the claimed advantages of rad approaches, What have RAD and extrem...

What have RAD and extreme programming got in common? What are the claimed advantages of these approaches? Both XP and RAD have as their common intention, and when their primary

Management parts, Discuss the management part of project management

Discuss the management part of project management

Quality standards, Quality Standards Quality Standards form a framework...

Quality Standards Quality Standards form a framework that helps organisations worldwide to develop products and services in the most efficient way. A quality Standard is a norm

Too much too soon, What is operational and behavioural symptoms

What is operational and behavioural symptoms

Line Balancing, What du you understand by line balancing

What du you understand by line balancing

Cobit, compare cobit 4.1 with cobit 5

compare cobit 4.1 with cobit 5

Explain how culture influences global product development, Question 1: ...

Question 1: (a) Critically evaluate joint venture and licensing as global market entry methods. (b) Explain and illustrate how a geocentric approach to global marketing i

Transaction cost theory could help the head of insurance, The Head of Insur...

The Head of Insurance at JKL Bank has been considering how to make efficiencies in the operation of the Car Insurance Business Unit. One option under consideration is to outsource

H U D guidelines, For an initial secure order under HUD guidelines, are yo...

For an initial secure order under HUD guidelines, are you authorized to remove exterior debris automatically?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd