Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Estimation Activities in Project Management , i want some on in expert in I...

i want some on in expert in IT project management and follow exactly and carefully the structure sheet.

Essential pre-requisites of a grievance procedure, Problem 1: Show the ...

Problem 1: Show the essential pre-requisites of a grievance procedure. Essential pre-requisites of a grievance procedure Problem 2: What are the objectives of Trade

Stages involved in the formal/rational approach to strategy, RF and JT are ...

RF and JT are both former international rugby players who, when they retired, formed their own business, WFH Trading Company.  The company that they established initially manufactu

Explain the levels of conventional planning, Question: (a) A team is ...

Question: (a) A team is any group of persons organised to work together or interdependently in order to cooperatively meet the needs of their customers by accomplishing a pu

Explain about the term project initiation document, Explain about the term ...

Explain about the term project initiation document. A project initiation document (PID) that is project proposal document or charter, is a report to illustrate a business case

How to measures customer satisfaction for the product, Quality ultimately i...

Quality ultimately is calculated in terms of customer satisfaction.) Surveyed before product delivery and after product delivery (and on-going on a periodic basis, using standar

Backward integration, Backward Integration A strategy in which an orga...

Backward Integration A strategy in which an organization builds competitive benefits by controlling the provider of the raw materials needed to make its products.

What are the advantages of division of labour, What are the Advantages of D...

What are the Advantages of Division of Labour? Advantages of Division of Labour: As very similar worker does the same work frequently:- a. It gains proficiency and ski

Appraisal process to help staff appreciate, KS, the Finance Manager of TZY ...

KS, the Finance Manager of TZY Company's Finance Department, is aware that it is approaching the time of year when he requirements to conduct staff appraisals. However, he is consc

Discuss the sources of national competitive advantage, Porter's Diamond is ...

Porter's Diamond is a useful framework that can help an organisation in identifying the extent to which it can build on home based national advantages to create competitive benefit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd