Explain what is the maximum possible output per week, Operation Management

Assignment Help:

An assembly line with 7 tasks is to be balanced. The longest task is 8 minutes, the shortest task is 2 minutes, and the sum of the task times is 53 minutes. The line will operate for 6 hours per shift, 1 shifts per day, 6 days per week.

What is the maximum possible output per week for this line?


Related Discussions:- Explain what is the maximum possible output per week

Describe how a company might benefit, Explain how a company might benefit f...

Explain how a company might benefit from the Contract Management Maturity Model. Can you suggest any viable reasons for a company's choosing not to conduct this assessment? If so,

Operations sequence analysis, Operations Sequence Analysis Being an ea...

Operations Sequence Analysis Being an early approach to process layouts operations sequence analysis develop a good scheme for arrangement of department graphically analysis t

Important functions of maintenance department, Problem 1: What are the ...

Problem 1: What are the important functions of maintenance department? Day to day activities Keeping the machinery, equipment, and services in proper working condition

Explain b2b marketing, Is B2B marketing really any different than B2C marke...

Is B2B marketing really any different than B2C marketing? Many believe that B2B marketing may actually be much more manageable than B2C marketing. How do you feel about that percep

Explain five key economic variables, Identify five key economic variables t...

Identify five key economic variables that could represent major opportunities or threats to a bank in your town or city. Identify which that you believe to be most important, and d

Difference between, Give difference between assembler, compiler and interpr...

Give difference between assembler, compiler and interpreter

Define the resources over and under capacity, Define the resources over and...

Define the resources over and under capacity. The resources over and under capacity: a. Over capacity: it is also called as spare capacity resources for example, staff

Explain were the colonists more responsible for winning it, Need reference/...

Need reference/cited for this question. • Were the British more responsible for losing the war or were the colonists more responsible for winning it? Use specific examples fr

Explain the four colour problem, The Four Colour Problem. Is it true that t...

The Four Colour Problem. Is it true that the countries on any given map can be coloured with four or fewer colours in such a way that adjacent countries are coloured differently?

Explain perfect competition, In which of the following market structures wo...

In which of the following market structures would X-inefficiency be most likely to exist? 1. Perfect competition 2. Monopoly 3. Oligopoly 4. Monopolistic competition

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd