Explain what design capacity would be needed, Operation Management

Assignment Help:

In a job shop, effective capacity is only 50% of design capacity, and actual output is 80% of effective output. What design capacity would be needed to achieve an actual output of 8 jobs per week?


Related Discussions:- Explain what design capacity would be needed

During the analysis of a process that was evaluated, What are some of the p...

What are some of the possible explanations for not finding any assignable causes

Explain old assembly line method, What changes in the work situation might ...

What changes in the work situation might account for the increase in productivity and the decrease in controllable rejects? What might account for the drop in absenteeism and the i

Lysosomes, Lysosomes Lysosomes were first discovered by Christian de Du...

Lysosomes Lysosomes were first discovered by Christian de Duve. Unlike other organelles which were detected by microscbpe, these were first discovered biochemically. Later, ele

Decreasing value a demerit of reducing project scope, Why is decreasing val...

Why is decreasing value a disadvantage of reducing project scope to accelerate a project?

Define conflict within a project team, What are the consequences of ignorin...

What are the consequences of ignoring a conflict within a project team?

Explain the training and explain the method that was used, Traditional lear...

Traditional learning methods include lectures, hands-on, on-the-job training, self-directed learning, apprenticeship, case studies, business games, role plays, behaviour modelling,

Define customer driven analytic to make managerial decisions, 1) What assum...

1) What assumptions are necessary when using customer driven analytics to make managerial decisions? 2) How does the IT strategy of 7/11 influence other aspects of the business

What needed to accurately predict capacity, 1) A process oriented layout wi...

1) A process oriented layout will minimize the total time spent on setting up machines? 2) By increasing the capacity of an operation you improve its efficiency. 3) Standard

Explain sales-force composite, List the specific weaknesses of each of thes...

List the specific weaknesses of each of these approaches to developing a forecast: a. Consumer surveys. b. Sales-force composite

Explain pipeline transportation system for treated water, The network in fi...

The network in figure below shows the pipeline transportation system for treated water from the treatment plant (node 1) to a city water supply system (node 14). The arc capacities

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd