Explain the welding process, Mechanical Engineering

Assignment Help:

All shell and head joints shall be double-welded butt joints with full penetration. In cases where double welding is impractical, the root pass shall be made by the GTAW process.

All welds for nozzles and manways shall be full penetration through the vessel wall. Where heavy wall vessels with small nozzle diameters are involved, an alternative method of full penetration may be permitted if prior written approval is obtained from the OWNER.

The layout of shell and head plates shall be made in such a manner that the manways, nozzles, and their reinforcing pads are not located in or on any of the weld seams.

Double-welded groove joints shall have their root passes back gouged to sound metal on the reverse side before proceeding with welding on that side.

All single-welded groove joints in nickel alloy, stainless steel, and ferritic steel containing more than two percent chromium shall be welded using a gas tungsten-arc or a gas metal-arc root pass with an inert gas back purge. The back purge shall be maintained for a minimum of two passes.

All welding including supports, clips, and structural parts shall be completed prior to postweld heat treatment.

Permanent welding backing bars other than consumable inserts are not permitted.

Temporary backing bars must match the chemical composition of the base metal being welded. After welding is complete, they shall be removed flush with the base metal without undercutting. All attachment areas shall be examined by magnetic particle or liquid penetrant methods.

Grinding and cleaning of stainless steels and non-ferrous material shall be done only with tools that will not leave detrimental deposits on the base metal; aluminum oxide or silicon carbide grinding wheels and austenitic stainless steel wire brushes shall be used. These tools shall not have been used previously on other than the material to be cleaned.

Peening is not permitted. The use of a needle gun for scale removal is not considered peening.

Welding shall not be performed on cast iron parts. If casting repairs are required, the proposed procedure shall be submitted to the OWNER for approval.

Tack welding may be used for alignment and to maintain root spacing. Tack welds shall be made in accordance with an approved welding procedure using the same electrode that will be used for the root pass and shall be deposited in such a manner as to facilitate incorporation in the weld.

Cracked or broken tack welds shall be chipped or ground out and thoroughly cleaned prior to being fused in with the final weld.

Cracked welds, surface porosity or welds having surface irregularities must be removed before welding resumes. Weld craters shall be completely filled before depositing subsequent weld beads.


Related Discussions:- Explain the welding process

Nozzle design loads, Q. Nozzle Design Loads? Minimum nozzle design load...

Q. Nozzle Design Loads? Minimum nozzle design loads shall be in accordance. F = Axial force on centre line of nozzle (lbs); Maximum Transverse Force =1.5F F R = Resultan

Discover the maximum torque, Discover the maximum torque: Discover the...

Discover the maximum torque: Discover the maximum torque that may be transmitted by the shaft of 400 mm diameter, if the shear stress is not to exceed 50 N/mm 2 . Solution

Mechanics of materials, how to find bending moment diagram of cantilever be...

how to find bending moment diagram of cantilever beam.any formula

Applications, applications of dynamically induced emf

applications of dynamically induced emf

Calculate the final velocities of the two masses, Calculate the final veloc...

Calculate the final velocities of the two masses: A mass of 10 kg moving along with a velocity of 10 m/sec along x direction follows another mass of 4 kg moving with 5 m/sec i

Refrigeration, A refrigeration system produces 40 kg/hr of ice at 0oC from ...

A refrigeration system produces 40 kg/hr of ice at 0oC from water at 25oC. Find the refrigeration effect per hour and TR. If it consumes 1 kW of energy to produce the ice,

Can you implement compatibility test, Q. Can you implement Compatibility te...

Q. Can you implement Compatibility test ? This test indicates the decrease in height of a mass of sand in a specimen tube with respect to its original height, under the actio

Conventional priority rules, Conventional Priority Rules  The standard ...

Conventional Priority Rules  The standard solution for production scheduling (routing and sequencing) difficulties is the utilization of priority rules. A priority rule is an o

AOC, The objective of the project is to protect damage of the DC motors. If...

The objective of the project is to protect damage of the DC motors. If the motor is not working it will be shown with red light, if working normally then green and if working at a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd