Explain the shrink factor of soil, Civil Engineering

Assignment Help:

Explain the Shrink Factor of Soil

In addition to the swell factor and its associated load factor, soil also has a shrink factor. While the first two relate the volume of an equal mass of bank soil in the ground with the loose mass deposited in stockpiles or dump trucks by excavation, the shrink factor relates the initial bank soil with the volume resulting from subsequent placement and compaction of the loose soil into earthen structures. 

Often this ratio is not a result of natural characteristics but is based on the construction specifications.  For example, clay soils used to construct a high density/low permeability containment layer for landfills are typically constructed in controlled lifts of a certain spread thickness which are then compacted to a final desired thickness. Typically, the soil is spread out over the work area in loose lifts about 8 inches thick.   Multiple passes with a compacting roller (sheep foot roller or vibratory smooth drum roller) are then performed to compact and knead the loose clay into a tight layer of about 6 inches thickness. This results in a post-compaction volume that is approximately 25% smaller than that of the initial loose placement volume.


Related Discussions:- Explain the shrink factor of soil

Stone, STONE Stone is a 'naturally available building material' used fr...

STONE Stone is a 'naturally available building material' used from the early age of civilization. It is available in the form of rocks, which is cut to needed size and shape an

Show the application of concrete crash barriers, Q. Show the application of...

Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl

Water piped scheme, how to use mood diagram to get f and other Re

how to use mood diagram to get f and other Re

Counter map, how will you determine the intrtvisibility of a point if the c...

how will you determine the intrtvisibility of a point if the counter map is given to you? explain by giving an exampe

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Engineering economics, Ask quA contractor has both a 3-cy and a 5-cy shovel...

Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 worki

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Calculate the poissons ratio, Calculate the Poissons Ratio: In separat...

Calculate the Poissons Ratio: In separate experiments, Young's Modulus and Rigidity Modulus of a material have been determined as 120 GPa and 50 GPa respectively. Calculate th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd