Explain the influence line-moment, Civil Engineering

Assignment Help:

Influence line-moment

1.  Replace the point of interest with an imaginary hinge.

2.  Rotate the beam one unit rotation by apply equal but opposite moments to each of the two beam sections.

 Note: when a point of interest is a support, this unit rotation can be achieved by simply lifting the point at the hinge location.

36_Influence line-moments.png

θ1 = b/L

θ2 = a/L

L = a+b


Related Discussions:- Explain the influence line-moment

Describe about the baur-leonhardt system, Describe about the Baur-Leonhardt...

Describe about the Baur-Leonhardt system The Baur-Leonhardt system is included in the third type of anchorages which work under the principle of looping tendon wires at the en

Necessity of air valves in pressurized pipelines, Q. Necessity of air valve...

Q. Necessity of air valves in pressurized pipelines? Air valves are broadly categorized into two major types: single air valves and double air valves. Single air valve comprise

Airport lighting, Airport Lighting: Lighting of Approach to Runway ...

Airport Lighting: Lighting of Approach to Runway A good system of identification of the runway when landing is to provide six transverse cross-bars of lights placed a

Highway pavement design, Explain the important factors affecting the design...

Explain the important factors affecting the design of pavement?

Backward and forward curved vanes in pumps, Backward curved vanes vs. forwa...

Backward curved vanes vs. forward curved vanes in pumps  Power of a pump is related to discharge as follows: Power = k 1 Q + (k 2 Q 2 / tan A) Where K 1 and K 2 are

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Concrete, What is compacting factor

What is compacting factor

Installation of band drains, Question For drained reclamation, what wil...

Question For drained reclamation, what will significance of smear zone bring by installation of band drains ? Answer Throughout installation of band drains, smear zon

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd