Explain the fireside transportation department projects, Operation Management

Assignment Help:

Fireside Tire Company, a manufacturer of radial tires for sport utility vehicles, sells its products in the automotive aftermarket and distribution them throughout the United States. Fireside has three tire production plants located in Allentown, Pennsylvania; Toledo, Ohio; and Macomb, Illinois (see map). Normally, Fireside ships tires from its plants to distribution centres, but truckload-size purchases typically are transported directly from plants to customer locations. All shipments to a region move under truck-load rates applying to a minimum weight of 40,000 pounds, or 400 cwt.

Fireside management is concerned about the most economical location for a distribution center to serve its southeaster region, consisting of North Carolina, South Carolina, Georgia, Florida, Mississippi, Alabama, and southeaster Tennessee. Although an Atlanta distribution center currently serves this region, Fireside management is concerned that the Atlanta location is not the most logistically sound alternative.

To help the logistics department conduct an analysis of this region's distribution center location using the grid method. Fireside's transportation department developed the following data based on projections for 2008:

2008 Shipments to Atlanta Grid Coordinates

From CWT RATE/CWT Mileage Horizontal Vertical

Toledo 15K $2.20 640 1,360 1,160
Macomb 5K $2.43 735 980 1,070
Allentown 11K $2.52 780 1,840 1,150

2008 Shipments From Atlanta Grid Coordinates

TO CWT Horizontal Vertical
Chattanooga 2,700 1,350 650
Atlanta 3,500 1,400 600
Tampa 4,300 1,570 220
Birmingham 2,800 1,260 580
Miami 5,300 1,740 90
Jacksonville 5,100 1,600 450
Columbia 2,200 1,600 650
Charlotte 2,900 1,590 740
Raleigh/Durham 2,200 1,700 800

CAse study Questions
1. Based on the available information is Atlanta the best location for a distribution center to serve the shouteast region? If not, what would you recommend?
2. The Fireside transportation department projects a 25 percent irate increase in 2013 from all of its transportation providers. How will this affect the southeastern location?
3. Marketing anticipates that the raliegh Durham market will grow by 3000 cwt in 2014, and tyhat fireside will serve the growth from Allentown. how will this affect Atlanta as a location?


Related Discussions:- Explain the fireside transportation department projects

Explain middle class population, Consider the table below. This time, the h...

Consider the table below. This time, the historical profitability of eight locations is listed in the table. Devise a regression equation and predict the profitability of a new sit

Define save money before announcing the restructuring plans, Should GM have...

Should GM have taken any additional steps to save money before announcing the restructuring plans?

Explain main reasons businesses safe guard the environment, What are the ma...

What are the main reasons businesses don't conserve natural resources or safe guard the environment?

Explain why is it important for a company to orient freshers, Why is it imp...

Why is it important for a company to orient a new employee to a job? What steps would you take to orient a new employee to do what they are supposed to do?

Explain what is the coefficient of determination, A large school district i...

A large school district is revaluating its teachers' salaries. They have decided to use regression analysis to predict mean teacher salaries at each elementary school. The research

Ppc in mass and flow production system, PPC in Mass and Flow Production Sys...

PPC in Mass and Flow Production System Continuous  production  is the  specialized  manufacturing  of identical  articles on which  the equipment  is  fully  engaged. Continuo

Explain what are the minimum and maximum cycle times, An assembly line with...

An assembly line with 17 tasks is to be balanced. The longest task is 2.1 minutes, and the total time for all tasks is 23 minutes. The line will operate for 480 minutes per day. a.

Define sociotechnical systems theory, Discuss sociotechnical systems theory...

Discuss sociotechnical systems theory and contrast it with the open systems theories of organization development?

Explain the decision variables for this problem, Problem 4: Comp-Max Comput...

Problem 4: Comp-Max Computers assembles computers and computer equipment. It is about to start production of three new types of computers, called model A, B, and C, respectively. E

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd