Explain the current maximum output of the process, Operation Management

Assignment Help:

I-mart is a discount optical shop that can fill most prescription orders in around 1 hour. The management is analyzing the processes at the store. There currently is one person assigned to each task below. The optometrist assigned to task B takes an hour off for lunch and the other employees work the entire day.

Task Time

A) Greet/register the patient 2 minutes/patient

B) Optometrist conducts eye exam 25 minutes/patient

C) Frame/lenses selection 20 minutes/patient

D) Glasses made (process can run 6 pairs of glasses at the same time) 60 minutes/patient

E) Final fi tting 5 minutes/patient

For a typical 10-hour retail day (10 a.m.-8 p.m.), the manager would like to calculate the following:

a) What is the current maximum output of the process per day (assuming every patient requires glasses)?

b) If another person were added, where would be the logical place?

c) What effect would a mail order lab (where the glasses are made off-site and returned in 5-7 days) have on the process?


Related Discussions:- Explain the current maximum output of the process

Describe opportunities to improve the system, Define the product you will b...

Define the product you will be offering at College Pretzel Company (CPC) in detail. Create any necessary documentation such as an engineering drawing or a bill of material for the

Intermittent and continuous operations, Explain intermittent and continuous...

Explain intermittent and continuous operations. Under what type of situation it would be used in automobile industry?

Explain cellular production is often conducted in a u-shaped, Cellular prod...

Cellular production is often conducted in a U-shaped (horseshoe-shaped) cell, rather than the rectangular cells shown in Figure 2.7b. What might be the advantages of this U shape?

Connected flow and disconnected flow system, Connected Flow and Disconnecte...

Connected Flow and Disconnected Flow System Such systems deliver very low unit costs, they are vulnerable; because of the absence of work-in-progress buffers, if one process f

Toyota Producttion assignment., Exercise 2: Use of a Grid Analysis (Weighte...

Exercise 2: Use of a Grid Analysis (Weighted Scoring Model) to Help Make the North American Plant Location Decision for the RX 330 This exercise illustrates how when deciding am

Explain operating cost & labour cost, A location analysis for Temponi Contr...

A location analysis for Temponi Controls, a small manufacturer of parts for high-technology cable systems, has been narrowed down to 4 locations. Temponi will need to train assembl

Explain some of the near-term and long-term results, As the industry watche...

As the industry watches to see how United Airlines' strategy performs against American Airlines' strategy, management at United Airlines is anxiously monitoring market signs to det

Productivity, how to calculate individual productivity

how to calculate individual productivity

How to perform a decision tree analysis for problem, Mountain States Electr...

Mountain States Electric Service is an electrical utility company serving several states in the Rocky Mountains region. It is considering replacing some of its equipment at a gener

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd