Explain the current maximum output of the process, Operation Management

Assignment Help:

I-mart is a discount optical shop that can fill most prescription orders in around 1 hour. The management is analyzing the processes at the store. There currently is one person assigned to each task below. The optometrist assigned to task B takes an hour off for lunch and the other employees work the entire day.

Task Time

A) Greet/register the patient 2 minutes/patient

B) Optometrist conducts eye exam 25 minutes/patient

C) Frame/lenses selection 20 minutes/patient

D) Glasses made (process can run 6 pairs of glasses at the same time) 60 minutes/patient

E) Final fi tting 5 minutes/patient

For a typical 10-hour retail day (10 a.m.-8 p.m.), the manager would like to calculate the following:

a) What is the current maximum output of the process per day (assuming every patient requires glasses)?

b) If another person were added, where would be the logical place?

c) What effect would a mail order lab (where the glasses are made off-site and returned in 5-7 days) have on the process?


Related Discussions:- Explain the current maximum output of the process

Explain what is the method of monitoring, What is the method of monitoring ...

What is the method of monitoring and reviewing in risk management?

Define activity a can be finished and not delay any activity, Using the dat...

Using the data in Table 13-4, determine the latest time activity A can be finished and not delay any activity? Table 13-4 The following represents a project with known activity tim

What are the various managing inventory tools, Q. What are the various mana...

Q. What are the various managing inventory tools? Raw material Materials and elements used to assemble or manufacture finished goods. Work-in-progress Incomplete f

Calculate sample mean & superimpose the frequency histogram, 1. (a) For the...

1. (a) For the measurement data presented below, draw a frequency histogram using a class width of 0.1 mm; calculate the sample means and superimpose their frequency histogram; com

Explain another name for a cause-and-effect diagram, Another name for a cau...

Another name for a cause-and-effect diagram is which of the following? Histogram Run chart Check sheet Fishbone diagram

Explain what is the efficiency process, An assembly line currently has five...

An assembly line currently has five workstations and the time required for each is shown below 1. 42sec 2. 49 sec. 3. 32 sec. 4. 47 sec. 5. 42 sec. What is the efficiency process?

Explain these with the actual service delivered, Q1 Evaluate the service to...

Q1 Evaluate the service to club members and casual flyers by completing a table similar to Table 3.1. Q2 Chart the five performance objectives to show the dif¬fering expectations

Compute the productivity in sales revenue/labour expense, Sailmaster makes ...

Sailmaster makes high-performance sails for competitive windsurfers. Below is information about the inputs and outputs for one model, the Windy 2000. Units sold 1,217 Sale price ea

Explain what were mcdonalds inventory turns, McDonalds Inventory $128.40Rev...

McDonalds Inventory $128.40Revenue $17, 140.50COGS $ 11943, 70Gross Profit $5,196.80 Wendy's Inventory: $54.40Revenue: 3148.90COGS: 1634.60Gross Profit: 1514.40 A. What were

Explain what is the firm''s code of conduct, Governance mechanisms are cons...

Governance mechanisms are considered to be effective if they meet the needs of all stakeholders, including shareholders. Governance mechanisms are also an important way to ensure t

Write Your Message!

Captcha
Free Assignment Quote