Explain flash butt welding, Civil Engineering

Assignment Help:

Q. Explain Flash Butt welding?

In this process the ends of two rails are kept at fixed distance apart and a mould (designed to suit the rail section ) is fitted on. The rail ends are then heated to yellow red temperature with a blowlamp. A swiveling type crucible containing iron oxide and aluminum powder to match the metallurgical composition of the rails is then ignited and the molten metal is poured into the mould so that the gap between the rail ends is filled up with over flow on all sides. The mould is then removed and excess metal is chipped off from the railhead while still hot. Later it is filed to railhead profile.

Normally it takes 45 minutes to weld a joint but by quick thermit process it can be done in 15 minutes. The joint can be brought into use immediately after welding.


Related Discussions:- Explain flash butt welding

Analyse the state of stress, Analyse the state of stress: For the cros...

Analyse the state of stress: For the cross-section shown in above figure, let us take b = 100 mm, d = 300 mm and M = 9 × 10 7 N mm and Q = 18 × 10 4 N and analyse the state

Transportation engineering, what is difference between stopping sight dista...

what is difference between stopping sight distance and overtaking sight distance

#surveying & levelling, expressions for calculating corrections for earth c...

expressions for calculating corrections for earth curvature

Moment of force on shoulders, During weight training,an athlete pulls a wei...

During weight training,an athlete pulls a weight of 500 N with his arms pulling on a handlebar connected to a universal machine by a cable.Find the moment of the force about the sh

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Define contaminants - underwater inspection of bridge, Define Contaminants ...

Define Contaminants - underwater inspection of bridge? There are various substances that may be inadvertently incorporated into the concrete matrix (e.g. glass, coal, gypsum),

Concrete, what are the appropriate methods of concreting

what are the appropriate methods of concreting

Show the replacement of loose rivets, Q. Replacement of loose rivets? i...

Q. Replacement of loose rivets? i) Slight slackness of rivet does not cause loss of rivet strength. ii) Renewal of slack rivets should be done only when the slack rivets are

Survey, who to we calculate the RL at first point.

who to we calculate the RL at first point.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd