Explain about the pre-tensioning systems, Civil Engineering

Assignment Help:

Pre-tensioning systems

In the previous unit we have seen different steps in a pretensioning operation. Tendon wires or strands (formed as a rope type arrangement made of  several tendon wires) are stretched and concrete is cast in the moulds, as shown in Figure. When sufficient strength is gained by concrete due to hardening, tendon wires may be cut from outside and jacks may be removed.

 

 

2484_Civil engineering.png


Related Discussions:- Explain about the pre-tensioning systems

Define the coefficient of permeability - hydraulic system, Define the Coeff...

Define the Coefficient of Permeability: (K) A measurement of the ability of the soil or an aquifer for the movement of water through it. Also termed "hydraulic conductivity", C

Measurement of surface runoff and infiltration, Surface runoff travelling o...

Surface runoff travelling over ground surface to reach receiving water involves the following events: i) Rainfall intensity exceeds soil's infiltration rate; ii) Excess water

Define latitude - transportation, Define Latitude - Transportation Lati...

Define Latitude - Transportation Latitude of a line is the distance that the line extends in a north or south direction. A line that runs towards north has positive latitude; a

How can a temporary diversion to laid, Q. How can a temporary diversion to ...

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months. Ans.- Temporary diversion

Penetration test, Penetration Test: A viscosity is measured indirectl...

Penetration Test: A viscosity is measured indirectly by the penetration of a standard needle under standard conditions of load, time and temperature. The test measures the ha

Method of construction of a bored cast-in-situ concrete pile, Q. Method of ...

Q. Method of construction of a bored cast-in-situ concrete pile? Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole

How to find back bearings?, Example: The following fore bearings were ...

Example: The following fore bearings were observed respectively for lines, AB, BC, CD, DE, EF and FG. Find out their back bearings: (i) 148°                          (ii

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd