Estimation of loading carrying capacity, Civil Engineering

Assignment Help:

Question

While designing mini-piles, should strength of grout be disused during estimation of loading carrying capacity?


Answer

While designing min-piles, there will two approaches existing-

(i) In first approach, an axial conflict provided by grout is mistreated and steel bars take up design loads only. This advance is a conservative one that leads to use of high strength bars such as Dywidag bar. One has to note that bending moment is not planned to be taken up by min-piles since of its slender geometry.

(ii) In second approach, it involves loads to be taken up by together grout and steel bars together. In this way, strain compatibility condition of grout and steel has to be pleased.

 


Related Discussions:- Estimation of loading carrying capacity

Deterioration in steel, How abrasion and earthquake causes deterioration in...

How abrasion and earthquake causes deterioration in steel structures

Project, I want to do project using ul design directory

I want to do project using ul design directory

Define recommendations for confined elastomeric pad, Define Recommendations...

Define Recommendations for confined elastomeric pad?  (a) Permissible limits for confined pressure on elastomer pad depends upon effectiveness of internal seal preventing it fr

Explain rebound hammer - underwater non-destructive testing, Explain Reboun...

Explain Rebound Hammer - Underwater non-destructive testing? The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condit

Rmc, about rmc and what are the safety measures taken and which licences ar...

about rmc and what are the safety measures taken and which licences are required

Briefly explain the concept of wind-driven ventilation, Problem (a) Br...

Problem (a) Briefly explain the concept of wind-driven ventilation and outlines its benefits over mechanical/electrical means of ventilation. (b) Various factors and guidel

Depth of boring for multi-storeyed building, Depth of Boring  for Multi-st...

Depth of Boring  for Multi-storeyed Building Peck has recommended that first drill hole is to be made up to depth at which the presence of a thick layer of soft clay with a hig

Pumps, largest centrifugal pumps

largest centrifugal pumps

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd