Earned value management is a systematic approach, Project Management

Assignment Help:

Question:

(a) Earned Value Management is a systematic approach to the integration and measurement of cost, schedule, and technical accomplishments in a project. List the benefits associated with this method.

(b) PK Motors Ltd embarked on a pilot project to produce 2000 units of a new model vehicle. The total cost of production is estimated at $27m and the project should be completed in 30 weeks. The rate of project progress is expected to be uniform and linear. At the end of week 18, the actual cost of work performed (ACWP) amounted to $17.1m and the number of cars produced was 600 units. As a project manager, you are requested to report the project status. Your answer should focus on the following:

(i) A graphical presentation of the project status
(ii) Cost Variance (CV)
(iii) Schedule Variance (SV)
(iv) Cost Performance Index (CPI)
(v) Schedule Performance Index (SPI)
(vi) Estimate To Complete (ETC)
(vii) Estimate At Completion (EAC)
(viii) Estimated time to complete

Consider the results of the Earned Value Analysis and briefly state whether the project is ahead or behind schedule and whether it is over or under budget.


Related Discussions:- Earned value management is a systematic approach

Describe incremental approach to testing by unit test, Describe the increme...

Describe the incremental approach to testing represented by the orderly unit (module) test. Unit (module) test: Along with the incremental approach to testing, every unit

Communication-coordination beneficial in project management, How are commun...

How are communication and coordination beneficial in project management software? Communication and coordination: Project software can give automatic report templates al

Tqm in manufacturing , Quality is actually built into the product durin...

Quality is actually built into the product during its manufacturing. The manufacturing of a product requires a host of activates involving different departments and sect

Internal and external environment of an organisation, This project requires...

This project requires you to choose an organisation of your own choice and discuss on the following with respect to your chosen organisation: External Environment Mega

Methods used to performance appraisal of workers, What are the methods used...

What are the methods used to performance appraisal of workers? The methods used within performance appraisal of workers are ranking method, Paired Comparison Technique, Forced

How is inventory procurement costs expenditure connected, How is Inventory ...

How is Inventory procurement costs expenditure connected? Inventory procurement costs that consists of expenditure connected along with as a. Its Receiving quotations b.

Project financing, Comparison between dept finance and ordinary share capi...

Comparison between dept finance and ordinary share capital

Why is necessary to plan an is project in detail before work, Give three re...

Give three reasons why this is necessary to plan an IS project in detail before starting work on this. Only the simplest projects that probably imply one developer working for

Phases of value engineering process, P hases of value engineering process ...

P hases of value engineering process I nvestigation phase: This phase investigates the background information, the technical input reports, the field data, the functiona

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd