Drive chain cleaning and adjustment , Mechanical Engineering

Assignment Help:

Drive Chain Cleaning and Adjustment : The service life of the drive chain depends on proper lubrication and adjustment. Poor maintenance can cause premature wear or damage to drive chain and sprockets. Under severe riding and use in the dusty areas frequent maintenance would be necessary.

STEPS

  • Remove the lower chain cover of the drive chain.
  • Keep a tray below the drive chain.
  • Clean the drive chain using kerosene with the help of a brush and air dry.
  • After drying, lubricate the drive chain with SAE 90 lubricant.
  • Check the slackness of drive chain. It should be between 20-30 mm.
  • If required adjust the drive chain. To adjust loosen the axle nut and sleeve nut.
  • Adjust the chain slackness by adjusting the chain adjuster nut.
  • Drive chain is adjusted equally on both the sides by ensuring the scale graduations on both the sides of the swing arm are coinciding with the notch on the adjusting plate
  • Clean the chain cover. Install the chain cover securely.

Important points to remember:

  • Chain slackness must be between 20-30 mm.
  • Open end drive chain lock plate should be fitted in the opposite direction of the chain rotation.

 


Related Discussions:- Drive chain cleaning and adjustment

Mathematics, solve the following differential equation: dy/dx-(1+1/x)y=y^2

solve the following differential equation: dy/dx-(1+1/x)y=y^2

Building a fermenter for a new product, The first stage of design assumes: ...

The first stage of design assumes: budget is approved, marketing research is complete, product can be made at a price below that which it can be sold, research and development is c

Torsion , in the torsion equation the term j/r is called

in the torsion equation the term j/r is called

Frames, what is a deficient frame?

what is a deficient frame?

What is hydrostatic extrusion, Q. What is Hydrostatic extrusion? • In t...

Q. What is Hydrostatic extrusion? • In the hydrostatic extrusion process the billet is completely surrounded by a pressurized liquid, except where the billet contacts the die.

Module site installation preparation, Q. Module Site Installation Preparati...

Q. Module Site Installation Preparation? The following tasks shall be accomplished at the Facility site prior to setting the modules on the piles: After module support piles

Sada, Ask question #ccMinimum 100 words accepted#

Ask question #ccMinimum 100 words accepted#

Elements of cad, Human Factor : The human factor is the key factor in th...

Human Factor : The human factor is the key factor in the success of CAD system. This concerns the training of the designer or the engineer without whom the CAD system become

Organisation set-up - construction of railway line, Organisation set-up: ...

Organisation set-up: The civil engineering department of the Railways is responsible for the maintenance of railway lines. The maintenance organisation consists of Chief Engi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd