The construction of a highway is broken into 14 activities as shown in the following table. Draw a bar chart of this construction project.

Activity ID

Description

Duration

Dependence

A

Survey & Layout

6

-----

B

Clear route

4

A

C

Excavate & grade

8

B

D

Plant & material

8

-----

E

Install drainage

5

B, A

F

Lay base-course

6

B, D

G

Lay pavement-course

5

F

H

Cut joints & cure

3

G

I

Dress shoulders

5

B

J

Make side drains

7

I

K

Construct curb

8

J

L

Paint signs on road

4

J, K

M

Signal & road signs

4

 L

N

Clean up

2

E, H, K

And then compute the total duration of the project and list the critical and non-critical activities. 


Related Discussions:- Draw a bar chart

Determination of the coupon rate, The partners are still unhappy about one ...

The partners are still unhappy about one of the features of your analysis, namely your assumption that the coupon rate of the bond is equal to 6% per annum. Their thinking is that

Percentage of sales method, Percentage of Sales Method A) Express the...

Percentage of Sales Method A) Express the various balance sheet items varying along with sales as percentage of sales as assume for year 2002 stock and net fixed assets amoun

Cvxcv, #questioxcvxcvn..

#questioxcvxcvn..

Requirements for raising loan, Requirements for Raising Loan Requireme...

Requirements for Raising Loan Requirements for Raising Loan are as follow: a) Subsidiaries of the company and History. b) Qualifications, ages, and names of the company's dire

Financial statement, Review the budget below and answer the questions follo...

Review the budget below and answer the questions following the budget. FINANCIAL ACCOUNTING—STATEMENT OF REVENUE AND EXPENSES Statement of Revenue and Expenses for Group Practice f

Calculate the weighted average cost of capital, Company XYZ stock is consid...

Company XYZ stock is considering the two new projects, Project A and Project B. The two projects have similar risk characteristics as the existing business. The managers forecast t

Draw a bar chart, The construction of a highway is broken into 14 activitie...

The construction of a highway is broken into 14 activities as shown in the following table. Draw a bar chart of this construction project. Activity ID Desc

Collection policy, Collection Policy The firm's collection policy may ...

Collection Policy The firm's collection policy may affect also our study.  The higher the cost of collecting accounts obtainable the lower the bad debt losses.  Therefore the

Compute the black-scholes price of one reverse convertible , Instructions ...

Instructions 1 This case study counts as part of your group project. 2 Project Group: You must complete this assignment together with the group that you initially registered

Executive share options plans, Executive Share Options Plans In a shar...

Executive Share Options Plans In a share option format, selected staff can be provided a number of share alternatives, each of which that provides the holder the right after a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd