Determine the weekly demand and lead time, Operation Research

Assignment Help:

Family Application specialises in selling major appliances for use in kitchen remodelling.  One of its more popular items is the SubZero refrigerator.  Over the past 40 weeks, the store has collected data regarding the weekly demand for this refrigerator.  On the basis of these data, the following demand distribution has been estimated:

The store's policy is to reorder up to 15 refrigerators whenever the inventory on hand

Weekly Demand                     Probability

0                                              0.25

1                                              0.15

2                                              0.15

3                                              0.25

4                                              0.1

5                                              0.1

reaches five or fewer at the end of a week. The holding cost for each refrigerator is $2 per week, and the cost of reordering is $50. If a customer wants a SubZero refrigerator and Family is out of stock, the customer will go elsewhere and the sale is lost. The company estimates that it suffers a goodwill cost of $40 for each lost sale.

Current inventory is seven refrigerators. Lead time for delivery can be described by the following distribution:

Lead Time                   Probability

1 week                         0.3

2 weeks                       0.5

3 weeks                       0.2

(a)  Conduct a 10-week simulation of Family's inventory situation regarding the SubZero refrigerator to determine the total cost for this period. Use random number generator of Microsoft Excel to determine the weekly demand and to determine the lead time.  

(b)  SubZero is  offering Family a new policy of automatically delivering five refrigerators every two weeks. Conduct a 10-week simulation of Family's inventory situation under this plan and determine the total cost for the 10-week period.

(c)  On the basis of your answers to part (a) and (b), what would you recommend to Family management regarding the supplier's offer?


Related Discussions:- Determine the weekly demand and lead time

Degrees of freedom, Determining Degrees of Freedom   One of the prer...

Determining Degrees of Freedom   One of the prerequisites for using chi square test is that we should calculate the number of degrees of freedom for the contingency table. T

Report writing - report writing presentation, REPORT WRITING The final...

REPORT WRITING The final step in research is to report the study  findings to those  who authorized the investigation. The American marketing association is  of the opinion  t

Replacement models - operation research model, These models are used whe...

These models are used when one must decide the optimal time to replace equipment for one reason or the other for instance, in the case of equipment whose efficiency dete

Evaluate a product from the view point of quality, This assignment requires...

This assignment requires you to evaluate a product from the view point of quality, both quality of design (as perceived by the user) and quality of conformance. To ensure that we a

First paper, discuss the seauencing decision problem for n jobs on two and ...

discuss the seauencing decision problem for n jobs on two and three machines

formulate the optimality equations, Each day you own 0 or 1 stocks of cert...

Each day you own 0 or 1 stocks of certain commodity. The price of the stock is a stochastic process that can be modeled as a Markov chain with transition rates as follows

Information resources - selection principles, INFORMATION RESOURCES - SELEC...

INFORMATION RESOURCES - SELECTION PRINCIPLES: Selection of materials for a library requires sagacity, adroitness and attention to people's needs for everything from books and

Assignment answer, Q2.Six Operators are to be assigned to five jobs with th...

Q2.Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignm

Linear programming, solve the following linear programming problem using si...

solve the following linear programming problem using simplex method maximize z=3x1+2x2 subject to the constraints: x1+x2 x1+x2 x1,x2>=0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd