Determine the weekly demand and lead time, Operation Research

Assignment Help:

Family Application specialises in selling major appliances for use in kitchen remodelling.  One of its more popular items is the SubZero refrigerator.  Over the past 40 weeks, the store has collected data regarding the weekly demand for this refrigerator.  On the basis of these data, the following demand distribution has been estimated:

The store's policy is to reorder up to 15 refrigerators whenever the inventory on hand

Weekly Demand                     Probability

0                                              0.25

1                                              0.15

2                                              0.15

3                                              0.25

4                                              0.1

5                                              0.1

reaches five or fewer at the end of a week. The holding cost for each refrigerator is $2 per week, and the cost of reordering is $50. If a customer wants a SubZero refrigerator and Family is out of stock, the customer will go elsewhere and the sale is lost. The company estimates that it suffers a goodwill cost of $40 for each lost sale.

Current inventory is seven refrigerators. Lead time for delivery can be described by the following distribution:

Lead Time                   Probability

1 week                         0.3

2 weeks                       0.5

3 weeks                       0.2

(a)  Conduct a 10-week simulation of Family's inventory situation regarding the SubZero refrigerator to determine the total cost for this period. Use random number generator of Microsoft Excel to determine the weekly demand and to determine the lead time.  

(b)  SubZero is  offering Family a new policy of automatically delivering five refrigerators every two weeks. Conduct a 10-week simulation of Family's inventory situation under this plan and determine the total cost for the 10-week period.

(c)  On the basis of your answers to part (a) and (b), what would you recommend to Family management regarding the supplier's offer?


Related Discussions:- Determine the weekly demand and lead time

Techniques of observation method, Techniques of Observation Method Obs...

Techniques of Observation Method Observation always involves some interaction between respondent and researcher in which researcher has an opportunity to watch respondent fu

Cross cultural communication in the workplace, This assignment requires you...

This assignment requires you to carry out the first part of a research project on the topic of "Cross cultural communication in the workplace". You can take any approach to this to

Manufacturing operation , You are a manager at a medium sized manufacturing...

You are a manager at a medium sized manufacturing operation that sells a customized product directly to the consumers and the data pattern is linear but it can have the occasion ra

Importance of normal distribution , Importance of Normal Distribution ...

Importance of Normal Distribution Normal distribution  plays  a very  important  role in  statistical  theory  and in  particular  in sampling theory. It has  been  found  th

Linear progaming, #questA paper mill produces two grades of paper viz., X a...

#questA paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y p

Two handed process chart of signing a latter, Two Handed process Chart of S...

Two Handed process Chart of Signing a Latter     A multiple  activity  chart  records the related  sequence of activities  of more  than one subject, men  and / or  machine  o

DECISION MODELS, CRITICAL EXAMINATION OF THE APPLICATION OF DECISION THEORY...

CRITICAL EXAMINATION OF THE APPLICATION OF DECISION THEORY TECHNIQUES OR MODEL IN BUSINESS DECISION MAKING IN NIGERIA

Linear programing, A paper mill produces two grades of paper viz., X and Y....

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Carry out resource levelling for equipment resource, Teesside Construction ...

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd