Determine the head added by the pump, Civil Engineering

Assignment Help:

Primary effluent wastewater at 60oF (v = 1.217 x 10-5) is pumped to the top of a trickling filter (TF) a total of 75 vertical feet through schedule-40 welded steel pipe. The flow rate is 8.64 mgd (6,000 gpm). The suction piping is 24 in diameter straight piping (velocity of 4.8 fps), has a length of 10 ft and an energy loss of 0.03 ft. The discharge piping is 18 inch diameter (velocity of 8.6 fps), has a length of 177 ft and an energy loss of 3.6 ft. The total length of the suction and discharge piping is 187 ft. Minor losses exist in the discharge piping only and total an equivalent length of 137 ft. The wet well and TF distribution arms are open to the atmosphere. The pump efficiency is 85%. 1.  Determine the head added by the pump hA:

1. Determine the head added by the pump hA:

hA = (PD/γ - PS/ γ) + ( v2 D/2g - v2 S/2g) + ZD - ZS + hf ZD - ZS = 75 ft

v2 dis/2g = (8.6) 2 /64.4 = 1.15 ft v2 suc/2g = (4.8) 2 /64.4 = 0.35 ft

total hf = 0.03 ft + 3.6 ft = 3.62 ft

hA = 0 + (1.15 ft - 0.35 ft) + 75 ft + 3.62 ft = 79.4 ft

2.  Determine the hydraulic horsepower required:   

whp = hAQ(sp gr)/3956=((79.4 ft)(6000 gpm)(1))/3956 = 120 HP

3.  Determine the brake horsepower required:

bhp = whp/pump efficiency = 120 HP / 0.85 = 142 HP

4.  The friction or heat horsepower is

bhp-whp = 142 HP - 120 Hp = 22 HP


Related Discussions:- Determine the head added by the pump

Bridge abutment be placed under an embankment, Question It should be necess...

Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with dive

Show the concrete pressure on formwork, Q. Relation of pouring rate and tem...

Q. Relation of pouring rate and temperature with concrete pressure on formwork Freshly placed concrete exerts pressure on formwork at the time of the placing operation. It's i

Construction mesurment, Measurement quantity of excavation, concrete, formw...

Measurement quantity of excavation, concrete, formwork as my assignment brief.

Roof truss, The angle between the members at the joint is 30°. Design the ...

The angle between the members at the joint is 30°. Design the members at the joint. Design also the connection of the members at the joint. The length of the principal rafter betw

Explain Rapid Mixing Tank and Flocculation Basin , Explain Rapid Mixing Tan...

Explain Rapid Mixing Tank For the chemical reactions to occur, the chemicals must be mixed with water for both coagulation and softening we need mixing of chemical wi

Major differences between sureties and security, Question What are majo...

Question What are major differences between sureties and security ? Answer During construction contracts, if a contractor fails to carry out works, employer would e

Stormwater, Design of the stormwater drainage system for the sub-division ...

Design of the stormwater drainage system for the sub-division Work needed: The following tasks require to be performed for the drainage network: Compute stormwater r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd