Determine the critical path, Business Economics

Assignment Help:

S M Construction has been awarded a contract to build a new manufacturing plant just outside Cardiff. The activity on arrow table below gives data on the activities involved in the plant's construction.

The total cost in completing the project in normal time is £2 million, excluding site overheads which are £8000 per week.

Table of Activities

Activity

Normal time (weeks)

Shortest time (weeks)

Reduction costs (per week)

1-2

6

4

£7000

1-3

8

4

£8000

1-4

5

3

£3000

2-4

6

3

£5000

2-5

5

3

£4000

3-6

10

8

£15,000

4-6

8

5

£6000

5-6

6

6

-

The board of directors of the company have asked you to produce a precedence (activity on node) diagram and to determine the following:

1. The critical path using normal times, the project's total duration and the total cost of completing the project.

2. The shortest time in which the project can be completed and the associated costs.

3. The lowest cost for which the project can be completed and the corresponding time.


Related Discussions:- Determine the critical path

Relationship between financial and physical capital, Question 1: (a) D...

Question 1: (a) Discuss the relationship that exists between financial capital and physical capital. (b) Analyse how a stock-market crash would drive an economy into a

Work of international monetary fund and world bank, Does the work of the In...

Does the work of the International Monetary Fund and World Bank overlap? Less developed countries turn to the: • International Monetary Fund to resolve debt repayment, exch

Importance of non profit organisations, (a) Show the importance of Non Pro...

(a) Show the importance of Non Profit Organisations in Small Island Economies. (b) Show the importance of Foreign Direct Investment in Small Island Economies. Comment on th

What is conditionality, What is Conditionality? Conditionality is the ...

What is Conditionality? Conditionality is the needs imposed onto countries as pre-conditions for loans. Into crisis situations member countries seek assist from the IMF for

What is meant by back-to-back term, It is significant that the contracts be...

It is significant that the contracts between the main contractor and the customer and between the key contractor and subcontractors are back-to-back; what is meant by that term?

Why are state approaches considered as unsuitable, Why are state approaches...

Why are state approaches occasionally considered as unsuitable for promoting development? Liberal economists’ argument government intervention really thwarts development. G

Compute the lp valuation, Consider another company, Lateco, which has just ...

Consider another company, Lateco, which has just received its fifth round of investment.  These rounds have been: Series A: CP ($5M FV) or converts to 5M shares of common. Se

Theory of cost, how starting assignment on this topic

how starting assignment on this topic

What do you understand by the term "anthropometry"?, QUESTION 1 (a) Wha...

QUESTION 1 (a) What, according to you, are the ergonomic problems associated with the use of visual display units? Describe the measures which can be taken to eliminate these p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd