A worker machine operation was found to involve 3.5 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The workers time averaged 2.3 minutes per cycle and the worker was given a rating of 120 percent(machine rating is 100 percent). Mid way through the study, the worker too a 10 minute rest break. Assuming an allowance factor of 11 percent of work time, determine the standard time for this job course not round intermediate calculation. Round your final answer to 2 decimal places.

Related Discussions:- Design of work systems

Define the upper and lower control limits, The overall average on a process...

The overall average on a process you are attempting to monitor is 50 units. the process standard deviation is 1.72. Determine the upper and lower control limits for a mean chart, i

Explain what causes conflict in organizations, What causes conflict in orga...

What causes conflict in organizations? Many of the organizational behaviour topics that have been addressed in the class thus far include the opportunity for conflict to emerge. Fo

Explain risks associated with relying on imperfect, No one (or no organizat...

No one (or no organization) would make a decision based off of imperfect information. However, for a variety of reasons, many times organizations have had to function and make deci

[email protected], Modelling – meaning and process, Certainty and uncertainty...

Modelling – meaning and process, Certainty and uncertainty in models, importance of understanding data before modelling , modelling with spreadsheet in simple decision situations.

Explain important part of strategic training, Why is evaluating training an...

Why is evaluating training an important part of strategic training?

Discuss the relationship between companies and profit motive, Discuss the r...

Discuss the relationship between these four features of capitalism. Companies, profit motive, competition and private property.

Explain what is the expected project length, Task time estimates for a prod...

Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Activity Time (in hours) Predecessors A 6.0 - B 7.2 __ C

Determine the biggest management challenge, What does Drucker see as the bi...

What does Drucker see as the biggest management challenge for the 21st century?  Answer: Improving the productivity of the office worker.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd