Design nominal reinforcement for staircase, Civil Engineering

Assignment Help:

Question

Given a 1meter high staircase resting on solid concrete, could it be adequate to design nominal reinforcement for staircase?


Answer

For design of staircase, there are three key scenarios-
(i) Stairs spans longitudinally -
This type of stairs refers to stairs spanning between landings only without any side supports. In case, staircase have to be designed as a beam between two end supports and main reinforcement is provided at bottom of staircase slabs.

(ii) Stairs spanning transversely -
This sort of staircase is supported by sidewalls only and it might also be supported by stringer beams. For case of sidewalls, it acts as a cantilever beam and main reinforcement are provided the top surface of slab. For case of staircase supported sideways by both sidewall and stringer beam, it have to be designed transversely with end supports as sidewall and stringer beam and strengthening is provided at bottom of the stairway.

(iii) Stairs resting on solid support -
For stairs resting on solid wires, only nominal steel reinforcement is provided to manage thermal and reduction cracking.

 

 


Related Discussions:- Design nominal reinforcement for staircase

Loss of prestress due to elastic shortening, Loss of prestress due to elast...

Loss of prestress due to elastic shortening At the transfer of prestress, tensile stresses of tendons are transferred to concretc in the form of compressive stresses. Due to t

structure analysis 2, what is ild for indeterminate beam and explain its p...

what is ild for indeterminate beam and explain its procedure

Haley''s formula in pile driving, Question What is major difference bet...

Question What is major difference between "hammer efficiency" and "coefficient of restitution" at what time using Haley's formula in pile driving?   Answer Hammer ef

Good surface regularity for sub-base in concrete pavement, Q. Good surface ...

Q. Good surface regularity for sub-base in concrete pavement? Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reas

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd