Question A The basic characteristic feature of Operations Research is that it employs mathematical representations or models to analyse problems. Explain the methodology of Operations Research.
Question B 1) Describe the Monte Carlo Simulation.2) Describe in brief the advantages and limitations of Simulation.
Question C 1) A Game refers to a situation of conflict and competition in which two or more competitors are involved in decision making in anticipation of certain outcome. Describe the following with respect to games.
2) An electric company is planning to develop and produce a new stabilized power supply system. The project can be described by the following activities.
S. No
Activity
Predecessor (s)
Time (days)
A
Market survey
-
15
B
Establish design
5
C
Electrical design
20
D
Test electrical design
3
E
Mechanical design
B,A
2
F
Review final design
D,E
G
Manufacture prototype
6
H
Test prototype
10
I
Schedule production
H,A
Construct network diagram for the project
A company manufactures 2 kinds of hats. Each hat of the I type needs twice as much as labour time as the II type. The company can manufacture a sum of 500 hats a day. The market re
Graphs of Time Series A time series is a sequence of values corresponding to successive points of time. Time series are graphed with time on the x axis and the oth
REPORT WRITING The final step in research is to report the study findings to those who authorized the investigation. The American marketing association is of the opinion t
Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignment
application area of linear programing problem
applications
The scientific method in O R study generally involves the followings three phases: 1. Judgment phase, 2. Research phase 3. Action phase
How can you integrate environmental concerns into production systems?
ONE SAMPLE RUNS TEST A number of methods have been developed fro judging the randomness of samples on the basis of the order in which teh observations are taken. It is
we have three reservoirs with daily supplies of15, 20 and 25 litres of fresh water respectively. on each day we must supply four cities A B C D whose demands are 8 10 12 and 15 res
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd